Question

Problem 1: A forensic audit firm has five audit jobs remaining at a point in time. The audits are labeled as jobs 1, 2, 3, 4
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a)

(1)

Critical ratio = Due date/ Time required for processing

As per sequencing rule, jobs with lowest critical ratio are sequenced first and so on.

Job 1 -> CR = 60/ 10 =6

Job 2 -> CR = 45/28 = 1.61

Job 3 -> CR = 30/30 = 1

Job 4 -> CR = 32/1 = 32

Job 5 -> CR = 31/ 2 =15.5

So we will sequence Job 3 first then 2, 1, 5 and 4.

Sequence Time required Due day Flow time Lateness (flow time- due date), -ve is 0
3 30 30 30 0
2 28 45 30+28=58 58-45=13
1 10 60 58+10=68 68-60=8
5 2 31 68+2=70 70-31=39
4 1 32 70+1=71 71-32=39

Average flow time= Total flow time/ number of jobs= (30+58+68+70+71)/5 = 59.4 days

Average days late = Total lateness/ number of jobs = (0+13+8+39+39)/ 5 =19.8 days

Average work in progress = Total flow time/ total time required = (30+58+68+70+71)/ (1+2+10+28+30) = 4.18

(2)

SPT is shortest processing time. As per this rule, sequencing is done such that job with shortest processing time is scheduled first and so on.

Sequence Time required Due day Flow time Lateness (flow time- due date), -ve is 0
4 1 32 1 0
5 2 31 1+2=3 0
1 10 60 3+10=13 0
2 28 45 13+28=41 0
3 30 30 41+30=71 71-30=41

Average flow time= Total flow time/ number of jobs= (1+3+13+41+71)/5 = 25.8 days

Average days late = Total lateness/ number of jobs = 41/ 5 =8.2 days

Average work in progress = Total flow time/ total time required = (1+3+13+41+71)/ (1+2+10+28+30) = 1.82

(3)

EDD is earliest due date. Sequencing is done with jobs due first and so on.

Sequence Time required Due day Flow time Lateness (flow time- due date), -ve is 0
3 30 30 30 0
5 2 31 30+2=32 32-31=1
4 1 32 32+1=33 33-32=1
2 28 45 33+28=61 61-45=16
1 10 60 61+10=71 71-60=11

Average flow time= Total flow time/ number of jobs= (30+32+33+61+71)/5 = 45.4 days

Average days late = Total lateness/ number of jobs = (0+1+1+16+11)/ 5 = 5.8 days

Average work in progress = Total flow time/ total time required =(30+32+33+61+71)/ (1+2+10+28+30) = 3.20

(b)

All performance measures against each rule are calculated in section (a)

(c)

Now the objective is to minimize the total number of late jobs in the sequence. Looking at the above performance data for each rule, we can access that SPT rule has lowest number of late job (1). Hence, SPT is an appropriate method to minimize the total number of late jobs.

Sequence as per SPT is 4-5-1-2-3.


Please give thumbs up/ likes if you consider my answer useful. Thank you!

Add a comment
Know the answer?
Add Answer to:
Problem 1: A forensic audit firm has five audit jobs remaining at a point in time....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • : A forensic audit firm has five audit jobs remaining at a point in time. The...

    : A forensic audit firm has five audit jobs remaining at a point in time. The audits are labeled as jobs 1, 2, 3, 4 and 5. The respective audit times (in days) and the remaining days before the due date are given in the table below. Audit job Time required Due (at the end of) day 1 11 61 2 29 45 3 31 31 4 1 33 5 2 32 Determine the job sequence using each of these...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • ABC Enterprises has five jobs that must be scheduled for production at a work center. Below...

    ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job.                                     Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9                                                                                                                            Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...

  • decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table....

    decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table. Jobs are logged as they arrive. Today is day 1 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: % (enter your response as a percentage The percentage utilization for the sequence developed using the EDD rule = rounded to two decimal places). Job Work (Processing) Time (Days) Job Due Date (Days) d)...

  • 5. A firm that specializes in desktop publishing for local charities has agreed to take on...

    5. A firm that specializes in desktop publishing for local charities has agreed to take on the following jobs. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Please use the dispatching rules suggested in the following box and complete all the calculation needed in order to provide the performance measures asked in the box. Today's date is 5. Please keep two decimal points. Job 1 Job...

  • 5. A firm that specializes in desktop publishing for local charities has agreed to take on...

    5. A firm that specializes in desktop publishing for local charities has agreed to take on the following jobs. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Please use the dispatching rules suggested in the following box and complete all the calculation needed in order to provide the performance measures asked in the box. Today's date is 5. Please keep two decimal points. Job 1 Job...

  • 5. A firm that specializes in desktop publishing for local charities has agreed to take on...

    5. A firm that specializes in desktop publishing for local charities has agreed to take on the following jobs. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Please use the dispatching rules suggested in the following box and complete all the calculation needed in order to provide the performance measures asked in the box. Today's date is 5. Please keep two decimal points. Job 1 Job...

  • ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​...

    ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​ (to resolve a​ tie, use the order in which the jobs were​ received): Sequence Job 1 ▼ N L M K O 2 ▼ K O L M N 3 ▼ K N L O M 4 ▼ N L M O K 5 ▼ N O K M L The total flow time for the sequence developed using the SPT rule​ = nothing...

  • Question 20, Math problem 20. The Mowry Machine Shop still has five jobs to be pro-...

    Question 20, Math problem 20. The Mowry Machine Shop still has five jobs to be pro- cessed as of 8 A.M. today (day 23) at its bottleneck opera- tion. The day when the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) Job А 11 10 22 10 8 В 13 8...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT