Question

: A forensic audit firm has five audit jobs remaining at a point in time. The...

: A forensic audit firm has five audit jobs remaining at a point in time. The audits are labeled as jobs 1, 2, 3, 4 and 5. The respective audit times (in days) and the remaining days before the due date are given in the table below.

Audit job

Time required

Due (at the end of) day

1

11

61

2

29

45

3

31

31

4

1

33

5

2

32

  1. Determine the job sequence using each of these priority rules: (1) CR, (2) SPT, (3) EDD
  2. Determine the performance of each rule using (1) average flow time, (2) average days late, and 3) average work in progress
  3. Determine the sequence which will minimize the total number of late jobs
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer a=

1=Critical ratio=Time remaining until due date/ Remaining processing time

Audit job

Time required

Due (at the end of) day

Critical Ratio Calculation

1

11

61

(61-0)/11=5.55

2

29

45

(45-0)/29=1.55

3

31

31

(31-0)/31=1 (lowest)

4

1

33

(33-0)/1=33

5

2

32

(32-0)/2=16

So we will place Job 3 first which will be completed a 31 days.

Audit job

Time required

Due (at the end of) day

Critical Ratio Calculation

1

11

61

(61-31)/11=2.73

2

29

45

(45-31)/29=0.48(lowest)

3

4

1

33

(33-31)/1=2

5

2

32

(32-31)/2=0.5

So we will place Job 2 second which will be completed a 31+29=60 days

Audit job

Time required

Due (at the end of) day

Critical Ratio Calculation

1

11

61

(61-60)/11=0.09

2

3

4

1

33

(33-60)/1=-27

5

2

32

(32-60)/2=-14

So we will place Job 4 third which will be completed a 31+29+1=61 days

Audit job

Time required

Due (at the end of) day

Critical Ratio Calculation

1

11

61

(61-61)/11=0.0

2

3

4

5

2

32

(32-61)/2=-14.5

So we will place Job 5forth and the final sequence will be

3-2-4-5-1

2=In case of the shortest processing time, we will arrange the jobs in the ascending order to processing time. So the sequence will be

4-5-1-2-3

3= In case of the earliest due date, the job with a least due date will be placed first followed by second and so on. So the sequence is=3- 5-4-2-1

Answer b=

CR:

Job time

Flow time

Due date

Days

Job

(days)

(days)

(days)

tardy

3

31

31

31

0

2

29

60

45

15

4

1

61

33

28

5

2

63

32

31

1

11

74

61

13

74

289

87

Average job flow time = Total job flow time / Number of jobs = 289 / 5= 57.8 days.

Average job tardiness = Total job tardiness / Number of jobs = 87/ 5 = 17.4 days.

Average number of jobs = Total flow time / Makespan = 289 / 74 = 3.9jobs

SPT

Job time

Flow time

Due date

Days

Job

(days)

(days)

(days)

tardy

4

1

1

33

0

5

2

3

32

0

1

11

14

61

0

2

29

43

45

0

3

31

74

31

43

74

135

43

Average job flow time = Total job flow time / Number of jobs = 135 / 5= 27 days.

Average job tardiness = Total job tardiness / Number of jobs = 43/ 5 = 8.6 days.

Average number of jobs = Total flow time / Makespan = 135/74 = 1.8 jobs

EDD

Job time

Flow time

Due date

Days

Job

(days)

(days)

(days)

tardy

3

31

31

31

0

5

2

33

32

1

4

1

34

33

1

2

29

63

45

18

1

11

74

41

6

74

235

26

Average job flow time = Total job flow time / Number of jobs = 235 / 5= 47 days.

Average job tardiness = Total job tardiness / Number of jobs = 26/ 5 = 5.2 days.

Average number of jobs = Total flow time / Makespan = 235/74 = 3.1 jobs

Answer C= EDD will minimize the total number of late jobs

Add a comment
Know the answer?
Add Answer to:
: A forensic audit firm has five audit jobs remaining at a point in time. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 1: A forensic audit firm has five audit jobs remaining at a point in time....

    Problem 1: A forensic audit firm has five audit jobs remaining at a point in time. The audits are labeled as jobs 1, 2, 3, 4 and 5. The respective audit times (in days) and the remaining days before the due date are given in the table below. | Audit job Time required 10 28 30 Due (at the end of day 60 45 30 32 31 le a) Determine the job sequence using each of these priority rules: (1)...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • ABC Enterprises has five jobs that must be scheduled for production at a work center. Below...

    ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job.                                     Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9                                                                                                                            Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table....

    decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table. Jobs are logged as they arrive. Today is day 1 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: % (enter your response as a percentage The percentage utilization for the sequence developed using the EDD rule = rounded to two decimal places). Job Work (Processing) Time (Days) Job Due Date (Days) d)...

  • 5. A firm that specializes in desktop publishing for local charities has agreed to take on...

    5. A firm that specializes in desktop publishing for local charities has agreed to take on the following jobs. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Please use the dispatching rules suggested in the following box and complete all the calculation needed in order to provide the performance measures asked in the box. Today's date is 5. Please keep two decimal points. Job 1 Job...

  • 5. A firm that specializes in desktop publishing for local charities has agreed to take on...

    5. A firm that specializes in desktop publishing for local charities has agreed to take on the following jobs. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Please use the dispatching rules suggested in the following box and complete all the calculation needed in order to provide the performance measures asked in the box. Today's date is 5. Please keep two decimal points. Job 1 Job...

  • 5. A firm that specializes in desktop publishing for local charities has agreed to take on...

    5. A firm that specializes in desktop publishing for local charities has agreed to take on the following jobs. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Please use the dispatching rules suggested in the following box and complete all the calculation needed in order to provide the performance measures asked in the box. Today's date is 5. Please keep two decimal points. Job 1 Job...

  • ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​...

    ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​ (to resolve a​ tie, use the order in which the jobs were​ received): Sequence Job 1 ▼ N L M K O 2 ▼ K O L M N 3 ▼ K N L O M 4 ▼ N L M O K 5 ▼ N O K M L The total flow time for the sequence developed using the SPT rule​ = nothing...

  • 5. A work center has five jobs assigned to it. They are labeled, in the order...

    5. A work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D, and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT