6. A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for the activity durations. Time estimates (weeks L Cost estimates ($) Activity Predecessor(s) Normal time Crashed time Normal cost Crashed cost 10 9 $6000 $8000 - 85 $1100 $2000 A 7 5 $3000 $3800 B 12 4 $4000 $6000 B 4 2 $5000 $6500 AD 6 3 $2500 $4000 CE $2800 $$3000 a. Draw the Activity-on-node (AON)...
Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None None B Cost Normal Crash 1000 1600 2000 2700 300 300 1300 1600 2 1 С 1 1 D A 7 3 E 6 3 B с 1000 5000 F 2 850 4000 1500 NA G D. E 4 2000 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity should you...