Question

Task Time Predecessor 1 0.2 - 2 0.4 1 3 0.1 1 4 0.4 2,3 5...

Task

Time

Predecessor

1

0.2

-

2

0.4

1

3

0.1

1

4

0.4

2,3

5

0.1

2

6

0.3

3,4

7

0.2

5

8

0.2

5,6

9

0.4

7,8

Consider the operations given in Table 1. 47 feet of the oor space along the conveyor is available for installing assembly stations around a closed loop conveyor system. Eeach station is made 6 feet long in order for the operators to work comfortably, and at least 1 feet clearance between stations (except between input and output stations).

  • Find the maximum number of stations on conveyor when the target production rate is 90 units per hr.
  • Find the maximum number of stations on conveyor when the target production rate is 120 units per hr.
  • Find the speed of conveyor when target production rate is 90 units per hr.
  • Find the speed of conveyor when target production rate is 120 units per hr.
  • Find the task to workstation assignments with Largest Candidate Rule when the target production rate is 90 units per hr.
  • Find the total space occupied by the workstations and clearances when the target production rate is 90 units per hr.
  • Find the task to workstation assignments with Largest Candidate Rule when the target production rate is 120 units per hr. Adjust the station-sizes using the method we covered in the class.
  • Find the allocated space occupied to each workstation, and total space occupied including clearances when the target production rate is 120 units per hr.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The Total Task time, T is 2.3 mins, as given.

When the target production rate is 90 units per hr (1.5 units per min), the Cycle time, C (Production Time/ Output) is 0.67 mins.

The theoretical minimum number of stations on conveyor, Nt is T/C rounded up to the next highest integer.

Hence, Nt = 2.3/0.67 = 3.45 = 4 stations

The corresponding Efficiency, Et = T/ (Nt x C) = 0.86

When the target production rate is 120 units per hr (2 units per min), the Cycle time, C is 0.5 mins.

Hence, the theoretical minimum number of stations on conveyor, Nt = 2.3/0.5 = 4.6 = 5 stations

The corresponding Efficiency, Et = 0.92

The task to workstation assignments with Largest Candidate Rule when the target production rate is 90 units per hr, is as tabulated below. Based on this, there are 4 stations (Na) for which the space needed is 27 feet (given that each station is 6 feet long, and there is 1 foot clearance between stations - except between input and output stations.

The corresponding actual Efficiency, E = T/ (Na x C) = 0.86

Task Task time Remaining unassigned time Feasible remaining tasks
WS1 1 0.2 0.466666667 2
2 0.4 0.066666667 None
WS2 3 0.1 0.566666667 4
4 0.4 0.166666667 5
5 0.1 0.066666667 None
WS3 6 0.3 0.366666667 7, 8
7 0.2 0.166666667 None
WS4 8 0.2 0.466666667 9
9 0.4 0.066666667

The task to workstation assignments with Largest Candidate Rule when the target production rate is 120 units per hr, is as tabulated below. Based on this, there are 6 stations for which the space needed is 41 feet (given that each station is 6 feet long, and there is 1 foot clearance between stations - except between input and output stations.

The corresponding actual Efficiency, E = 0.77

Task Task time Remaining unassigned time Feasible remaining tasks
WS1 1 0.2 0.3 3
3 0.1 0.2 None
WS2 2 0.4 0.1 5
5 0.1 0 None
WS3 4 0.4 0.1 None
WS4 6 0.3 0.2 7, 8
7 0.2 0 None
WS5 8 0.2 0.3 None
WS6 9 0.4 0.1
Add a comment
Know the answer?
Add Answer to:
Task Time Predecessor 1 0.2 - 2 0.4 1 3 0.1 1 4 0.4 2,3 5...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT