Question

For each scenario, indicate how much revenue and, when applicable, expense are recognized in 2019. A. Company A enters into a contract for the provision of multiple deliverables to a customer in January, 2019. The selling price is $200,000. If each of th

For each scenario, indicate how much revenue and, when applicable, expense are recognized in 2019.

A. Company A enters into a contract for the provision of multiple deliverables to a customer in January, 2019. The selling price is $200,000. If each of the three components of the contract were sold separately, the selling price would be $120,000, $80,000, and $20,000. The first component is equipment, which was delivered in 2019. The second component is a software upgrade that will be provided in 2020, when its development has been completed. The third component is technical support, which will be provided over the next three years (2019, 2020, and 2021). 60% of the selling price was collected up front, with the other 40% being collected in January, 2020. What is the amount of revenue (ignore expenses) reported in 2019?

B. Company B signs a contract to build a new road for $2,000,000 over 3 years. The projected cost of the construction is $1,500,000. At the end of 2019, the construction company has reasonably estimated that 40% of the contract had been completed during the year. It has no concerns about collectability. In fact, it collected a $550,000 progress payment in 2019. What is the amount of 1) revenue and 2) expense reported in 2019?

C. Company C sells some merchandise to a customer for $1,000 on credit. The merchandise has a cost of $750. The customer will pay $100 monthly payments. In 2019, the customer made 8 payments. Since collectability is an issue, Company C decided to use the installment method. What is the amount of 1) revenue and 2) expense reported in 2019?

D. Same information as in transaction C above, except that Company C used the cost recovery method. What is the amount of 1) revenue and 2) expense reported in 2019?


0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
For each scenario, indicate how much revenue and, when applicable, expense are recognized in 2019. A. Company A enters into a contract for the provision of multiple deliverables to a customer in January, 2019. The selling price is $200,000. If each of th
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • On January 2, 2019, TI enters into a contract with Drewry Corp. to build a new...

    On January 2, 2019, TI enters into a contract with Drewry Corp. to build a new piece of equipment. The contract price is $3 million, and construction is expected to take 18 months. Drewry is billed and pays $1,500,000 of the contract price on January 2, 2019, and will pay the balance at completion. TI estimates that the cost of construction will be $2.2 million. Drewry includes two performance bonuses in the contact: • U.S. Bonus: If the equipment design...

  • On July 1, 2019, Grams Construction, Inc. agreed to construct a factory for a customer. The...

    On July 1, 2019, Grams Construction, Inc. agreed to construct a factory for a customer. The contract called for payments to Grams totaling $2 million. Grams has correctly determined that it is appropriate to recognize revenue over time, and it uses its costs as a measure of completion. The same cost information is used to determine the portion of the contract price Grams is entitled to receive. The following information describes the costs incurred and expected remaining costs at December...

  • The Five-Step Revenue Recognition Model A. Step 1: Identify the Contract(s) with a Customer B. Step...

    The Five-Step Revenue Recognition Model A. Step 1: Identify the Contract(s) with a Customer B. Step 2: Identify the Performance Obligations in the Contract C. Step 3: Determine the Transaction Price D. Step 4: Allocate the Transaction Price to the Performance Obligations in the Contract E. Step 5: Recognize Revenue When (or as) the Entity Satisfies a Performance Obligation F. Practical Expedients in Applying the Model G. Applying the Model to Contract Modifications C3-1 Applying the 5-step model (LO 3-1)...

  • 23) A right of return exists when: A) the customer is entitled to a full or...

    23) A right of return exists when: A) the customer is entitled to a full or partial refund. B) the customer is entitled to a credit against amounts owed. C) the customer is entitled to another product in exchange. D) any one of these conditions is met. 19) Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project and the requirements for recognizing revenue over time are met. The total estimated...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On December 1, 2019, Coburn Consulting Ltd. signed a contract with Burke Inc., which obligated Coburn...

    On December 1, 2019, Coburn Consulting Ltd. signed a contract with Burke Inc., which obligated Coburn to provide Burke with 16 hours of consulting services per month from January through December of 2020. The contract requires Burke to pay a total of $67,200 for these services, with payments of $5,600 due at the end of each month. Coburn has provided similar services to Burke in the past and has always collected its fees on a timely basis. Requirement Using IFRS...

  • On December 1, 2019, Coburn Consulting Ltd. signed a contract with Burke Inc., which obligated Coburn...

    On December 1, 2019, Coburn Consulting Ltd. signed a contract with Burke Inc., which obligated Coburn to provide Burke with 16 hours of consulting services per month from January through December of 2020. The contract requires Burke to pay a total of $67,200 for these services, with payments of $5,600 due at the end of each month. Coburn has provided similar services to Burke in the past and has always collected its fees on a timely basis. Requirement Using IFRS...

  • 1. On January 1, 2020, Jim Beam Company sold goods to a customer and received a...

    1. On January 1, 2020, Jim Beam Company sold goods to a customer and received a non interest bearing installment note requiring payments of $15,000 annually for six years. The first payment was received by Jim Beam Company on January 1, 2020. The prevailing rate of interest for this type of note is 8%.The total sales revenue Jim Beam Company would record for this sale on January 1, 2020 is : A)$90,000 B) $69,343 C) $74,891 D)$15,000 2. Johnnie Walker...

  • In 2020, Dixon Construction Company was awarded a contract to construct an interchange on Highway 30...

    In 2020, Dixon Construction Company was awarded a contract to construct an interchange on Highway 30 at a total contract price of $15,000,000. Construction is expected to take two years to complete. The estimated total costs of the project are $12,000,000. Dixon uses the percentage-of-completion method to account for long-term contracts. During the first year cost of construction totaled $7,200,000 and the total estimated costs for the project are unchanged. a)   Prepare the entry to record 2020 construction costs of...

  • JANUARY 2019. QUESTIONS Urban plc, a company that prepares its a company that prepares its financial statements to 3...

    JANUARY 2019. QUESTIONS Urban plc, a company that prepares its a company that prepares its financial statements to 31 December cach year involved in the construction and repair of city centre student accommod e r of inancial statements for the year ended 31 December 2018 can be finalised, outstanding issues need to be resolved. outstanding icments for them and repair of ancial staten need to be resor ended 31 Decennice stude ntre student accommodation. Before the succesusly and Urbcontract. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT