In 2020, Dixon Construction Company was awarded a contract to construct an interchange on Highway 30 at a total contract price of $15,000,000. Construction is expected to take two years to complete. The estimated total costs of the project are $12,000,000. Dixon uses the percentage-of-completion method to account for long-term contracts. During the first year cost of construction totaled $7,200,000 and the total estimated costs for the project are unchanged.
a) Prepare the entry to record 2020 construction costs of $7,200,000 paid in cash.
Dr. blank blank
Cr. blank blank
b) Prepare the entry to record the 2020 progress billings of $4,000,000 to the customer.
Dr. blank blank
Cr. blank blank
c) Prepare the entry to record the $3,500,000 payments on the contract received during 2020.
Dr. blank blank
Cr. blank blank
d) Prepare the necessary year-end entry to recognize the profit to date.
Dr. blank blank
Cr. blank blank
Dr./Cr. blank blank
e) What is the amount of gross profit that will
appear on the income statement?
blank
Choices:
1,800,000
3,500,000
4,000,000
7,200,000
7,200,000
9,000,000
Cash
Accounts Receivable
Construction Revenue
Billings on contracts
Construction Expense
Solution: (Amount in $)
Part A. Journal Entry to record expenses paid in cash
Date | Particular | Amount Dr | Amount Cr |
Construction cost A/c ( Work in Progress ) Dr | 7,200,0000 | ||
To Cash A/c. | 7,200,000 |
Part B: Progressive billing to customer
Date | Particular | Amount Dr | Amount Cr |
Accounts receivable A/c. Dr | 4,000,000 | ||
To Billings on construction contract | 4,000,000 |
Part C: Payment received
Date | Particular | Amount Dr | Amount Cr |
Cash A/c. Dr | 3,500,000 | ||
To Accounts receivable A/c | 3,500,000 |
Part D:
Date | Particular | Amount Dr | Amount Cr |
Profit and Loss A/c Dr | 7,200,000 | ||
To Construction cost A/c. | 7,200,000 | ||
( being expenses Transferred to P& L Account ) | |||
Construction Revenue A/c. Dr | 9,000,000 | ||
To Profit And Loss A/c. | 9,000,000 | ||
( Revenue recognizes based on percentage completion method & transferred to Profit and Loss A/c.) |
Note: Net Proft will Be 9,000,000 - 7,200,000 = 1,800,000.
Part E:
1,800,000 the amount of gross profit that will appear on the income statement
Note:
1. Percentage of completion & revenue to recognize
Percentage of completion = 7,200,000 / 12,000,000 * 100 = 60%
Revenue to recognize
= Percentage of completion * Total revenue of contract
= 60% * 15,000,000 = 9,000,000
2. As there is no indirect expense mentioned in question Net profit and Gross Profit for the year will same.
In 2020, Dixon Construction Company was awarded a contract to construct an interchange on Highway 30...
grand construction company was awarded a contact to construct an interchange at the junction of u.s 94 and highway 30 at atotoal contract price of 8000000$. the estimated total cost to complete the project were 6000000$. Cooper Construction Company had a contract starting April 2012, to construct a $9,000,000 building that is expected to be completed in September 2014, at an estimated cost of $8,250,000. At the end of 2012, the costs to date were $3,795,000 and the estimated total...
1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...
Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred costs of $279,500, billed its customer for $204,500, and collected $170,500. At December 31, 2020, the estimated additional costs to complete the project total $150,500. Prepare Cheyenne’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...
Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Coronado’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
Bridgeport, Inc. began work on a $7,043,000 contract in 2020 to construct an office building. During 2020, Bridgeport, Inc. incurred costs of $1.891,800, billed its customers for $1,315,000, and collected $939,000. At December 31, 2020. the estimated additional costs to complete the project total $3,363.200. Prepare Bridgeport's 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does not...
Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred costs of $295,500, billed its customer for $200,500, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $155,645. Prepare Vaughn’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
(Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of...
Below is information related to a construction contract for company ABC. The contract price is 9 million. 2019 2020 2021 2022 Costs incurred (accumulated) to date $ 1,500,000 $ 4,000,000 $ 4,750,000 Estimated costs to complete the project 3,400,000 700,000 0 Customer billings (Billings) 4,000,000 3,000,000 2,000,000 Cash Received from Customer 0 4,000,000 3,000,000 2,000,000 TEACHER NOTE: I am repeating the table with summarized numbers in case your device does not allow you to view the entire table above. M...