Question

Below is information related to a construction contract for company ABC. The contract price is 9...

Below is information related to a construction contract for company ABC. The contract price is 9 million. 2019 2020 2021 2022 Costs incurred (accumulated) to date $ 1,500,000 $ 4,000,000 $ 4,750,000 Estimated costs to complete the project 3,400,000 700,000 0 Customer billings (Billings) 4,000,000 3,000,000 2,000,000 Cash Received from Customer 0 4,000,000 3,000,000 2,000,000

TEACHER NOTE: I am repeating the table with summarized numbers in case your device does not allow you to view the entire table above. M = millions k = thousands 2019 2020 2021 2022 Costs incurred (accumulated) to date $ 1.5M $ 4M $ 4.75M Estimated costs to complete the project 3.4M 700k 0 Customer billings (Billings) 4M 3M 2M Cash Received from Customer 0 4M 3M 2M Instructions:

1. Assuming the company uses the Percentage of Completion method, prepare all the necessary inputs for 2020 only. (4.5 points)

2. Assuming the company uses the Percentage of Completion method, prepare the section in the 2020 Balance Sheet that applies. (3 points)

3. How much is the balance of the Construction in Progreso account as of 12/31/2021? (1.5 point)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Part 1

Answer 1
Year 2020 2021 2022
Cost incurred during the year (For year 2 = 4000000-1500000) (For Year 3 = 4750000- 4000000) $     1,500,000 $       2,500,000 $             750,000
Cumulative cost incurred at end of year $     1,500,000 $       4,000,000 $         4,750,000
Cumulative cost incurred at end of year $     1,500,000 $       4,000,000 $         4,750,000
Add: Estimated costs to complete as of year-end $     3,400,000 $          700,000 $                          0
Total estimated cost $     4,900,000 $       4,700,000 $         4,750,000
Cumulative cost incurred at end of year $     1,500,000 $       4,000,000 $         4,750,000
Divided by: Total estimated cost $     4,900,000 $       4,700,000 $         4,750,000
Percentage of completion 30.6122449% 85.1063830% 100.0000000%
Revenue recognized till the date (9000000 * percentage of completion) $     2,755,102 $       7,659,574 $         9,000,000
Less: Revenue recognized up to earlier year $                      0 $       2,755,102 $         7,659,574
Revenue recognized in current year $     2,755,102 $       4,904,472 $         1,340,426
Revenue recognized in current year $     2,755,102 $       4,904,472 $         1,340,426
Less: cost incurred during the year $     1,500,000 $       2,500,000 $             750,000
Gross Profit (Loss) $     1,255,102 $       2,404,472 $             590,426
Date General Journal Debit Credit
2020 Construction in progress         1,500,000
Various Accounts (materials/cash etc.)           1,500,000
(To record cost incurred in Progress.)
2020 Accounts receivable         4,000,000
Billings on construction contract           4,000,000
(To record Billings to Customer.)
2020 Cash         4,000,000
Accounts receivable           4,000,000
(To record cash collected from customer.)
2020 Construction in progress         1,255,102
Cost of construction         1,500,000
Construction Revenue           2,755,102
(To record recognize Revenue and profit.)

Part 2

Year 2020
Account receivable at beginning $                      0
Add: Amount billed $     4,000,000
Less: Cash received $   (4,000,000)
Account receivable at Ending $                    -  
Billing Amount $     4,000,000
Cumulative Billing amount $     4,000,000
Partial balance sheet (2020)
Current liability
Billings ($4,000,000) in excess of cost and profit ($2,755,102) (4000000-2755102) $     1,244,898

Part 3

Year 2020 2021
Beginning Construction in progress $                      0 $       2,755,102
Add: Cost incurred $     1,500,000 $       2,500,000
Add: Gross profit(loss) $     1,255,102 $       2,404,472
Ending Construction in progress $     2,755,102 $       7,659,574
Balance of the Construction in Progreso account as of 12/31/2021 $       7,659,574
Add a comment
Know the answer?
Add Answer to:
Below is information related to a construction contract for company ABC. The contract price is 9...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...

  • On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2.475,000 cash was collected. The project was completed in 2023 after additional costs of...

  • Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates...

    Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a...

    (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...

  • LO5-9 Concept Check: Revenue Recognition Over Time Robertson Construction entered into a contract to construct a...

    LO5-9 Concept Check: Revenue Recognition Over Time Robertson Construction entered into a contract to construct a tunnel for a fixed price of $12,000,000. Robertson recognizes revenue over time according to percentage of completion. Here are some facts: Estimated Additional Cost to Complete $6,000,000 2,000,000 Cost incurred $ 3,000,000 5,000,000 2,500,000 2021 2022 2023 How much revenue would Robertson recognize in 2021? a. $4,000,000 b. $5,000,000 $6,000,000 d. $12,000,000 LO5-9 Concept Check: Revenue Recognition Robertson Construction entered into a contract to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT