Question

(Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a...

(Long-Term Contract with Interim Loss)

On May 1, 2020, Jackson Construction Company contracted to

construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual

contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022

are

given below.

2020

2021

2022

Contract costs incurred during the year

$3,400,000

$2,400,000

$2,900,000

Estimated costs to complete the contract at 12/31

4,600,000

3,100,000

-0-

Billings

1,200,000 4,100,000 4,300,000

Instructions

(a)

Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a

result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)

(b)

Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of

this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore incomes taxes.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Price 9600000 9600000 9600000
2020 2021 2021
Cost to date 3400000 5800000 8700000
Estimated cost to complete 4600000 3100000 0
Progress billing to date 1200000 4100000 4300000
Estimated total cost         80,00,000                          89,00,000                           87,00,000
Estimated gross profit        16,00,000                            7,00,000                             9,00,000
a) Percentage of completion Caln
Gross Profit recognized in 2020           6,80,000 (3400000/8000000*1600000)
Loss recognized in 2021         -2,23,820 (5800000/8900000)*700000-680000
Gross Profit recognized in 2022 443820 (900000-680000+223820)
b) Completed contract method
Gross Profit recognized in 2017 0
Gross Profit recognized in 2018 0
Gross Profit recognized in 2019           9,00,000
Hi mate,
I would be grateful to you if you can provide a thumbs up and write one beautiful comment. It will improve my rating and let me continue my journey here.
In case of doubt, please comment. I will consider myself fortunate if I can help you.
All the best for your bright future.
Add a comment
Know the answer?
Add Answer to:
(Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted...

    * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022:...

  • *P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020,...

    *P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: 2020 2021 2022 Contract costs incurred during the year $2,700,600 $2,503,700 $2,125,700 Estimated costs to complete the contract at 12/31 3,729,400 2,125,700 –0– Billings...

  • On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabr...

    On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...

  • On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...

  • Problem 18-10 On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for...

    Problem 18-10 On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,340,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2019 2018 $2,811,600 $2,152,400 $2,336,000 2,336,000 Contract costs incurred during the year Estimated costs to complete the contract at3,578,400 12/31 Billings...

  • On March 1, 2017, Larkspur Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2017, Larkspur Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,052,800 $2,254,300 $1,962,900 Estimated costs to complete the contract at 12/31 3,307,200 1,962,900 –0– Billings...

  • Problem 18-10 On March 1, 2017, Culver Construction Company contracted to construct a factory building for Fabrik Manuf...

    Problem 18-10 On March 1, 2017, Culver Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2019 $1,962,900 Contract costs incurred during the year Estimated costs to complete the contract at 12/31 Billings to Fabrik during the year...

  • On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel...

    On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Crane estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. Contract costs incurred to date Estimated...

  • CALCULATOR PRINTER VERSION BACK Problem 18-10 On March 1, 2017, Riverbed Construction Company contracted to construct...

    CALCULATOR PRINTER VERSION BACK Problem 18-10 On March 1, 2017, Riverbed Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,490,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,907,000 $2,465,800 $1,987,200 Estimated costs to complete the contract...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT