Question

* (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted...

*

(Long-Term Contract with an Overall Loss)

On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022:

At

At

At

12/31/20

12/31/21

12/31/22

Contract costs incurred to date

$ 600,000 (2020)

$1,500,000 (2021)

$2,750,000 (2022)

Estimated costs to complete the contract

1,800,000 (2020)

1,200,000 (2021)

-0- (2022)

Billings to Sicily

400,000

1,200,000

2,400,000

Instructions

(a)

Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a

result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)

(b)

Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of

this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Price                                                           26,00,000.00                            26,00,000.00            26,00,000.00
2020 2021 2021
Cost to date                                                                  6,00,000                                 15,00,000                 27,50,000
Estimated cost to complete                                                          18,00,000.00                           12,00,000.00                                -  
Progress billing to date                                                             4,00,000.00                           12,00,000.00            24,00,000.00
Estimated total cost                                                           24,00,000.00                            27,00,000.00            27,50,000.00
Estimated gross profit                                                             2,00,000.00                            -1,00,000.00             -1,50,000.00
a) Percentage of completion Caln
Gross Profit recognized in 2020                                                                      50,000 (600000/2400000*200000)
Loss recognized in 2021                                                                 -1,05,556 (1500000/2700000*-100000)-50000
Loss recognized in 2022                                                                    -94,444 -150000-50000+105555.56
b) Completed contract method
Gross Profit recognized in 2017 0
Gross Profit recognized in 2018 0
Loss Profit recognized in 2019                                                                 -1,50,000
Hi mate,
I would be grateful to you if you can provide a thumbs up and write one beautiful comment. It will improve my rating and let me continue my journey here.
In case of doubt, please comment. I will consider myself fortunate if I can help you.
All the best for your bright future.
Add a comment
Know the answer?
Add Answer to:
* (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a...

    (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...

  • *P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020,...

    *P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel...

    On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Crane estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. Contract costs incurred to date Estimated...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Cullumber estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sunland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

  • On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: 2020 2021 2022 Contract costs incurred during the year $2,700,600 $2,503,700 $2,125,700 Estimated costs to complete the contract at 12/31 3,729,400 2,125,700 –0– Billings...

  • On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...

    On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $ 1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At...

  • On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabr...

    On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...

  • On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...

  • Problem 18-11 On July 1, 2017, Sheffield Construction Company Inc. contracted to build an office building...

    Problem 18-11 On July 1, 2017, Sheffield Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Sheffield estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 $273,600 1,246,400...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT