(Long-Term Contract with an Overall Loss)
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022:
At
At
At
12/31/20
12/31/21
12/31/22
Contract costs incurred to date
$ 600,000 (2020)
$1,500,000 (2021)
$2,750,000 (2022)
Estimated costs to complete the contract
1,800,000 (2020)
1,200,000 (2021)
-0- (2022)
Billings to Sicily
400,000
1,200,000
2,400,000
Instructions
(a)
Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a
result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)
(b)
Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of
this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)
Price | 26,00,000.00 | 26,00,000.00 | 26,00,000.00 |
2020 | 2021 | 2021 | |
Cost to date | 6,00,000 | 15,00,000 | 27,50,000 |
Estimated cost to complete | 18,00,000.00 | 12,00,000.00 | - |
Progress billing to date | 4,00,000.00 | 12,00,000.00 | 24,00,000.00 |
Estimated total cost | 24,00,000.00 | 27,00,000.00 | 27,50,000.00 |
Estimated gross profit | 2,00,000.00 | -1,00,000.00 | -1,50,000.00 |
a) Percentage of completion | Caln | ||
Gross Profit recognized in 2020 | 50,000 | (600000/2400000*200000) | |
Loss recognized in 2021 | -1,05,556 | (1500000/2700000*-100000)-50000 | |
Loss recognized in 2022 | -94,444 | -150000-50000+105555.56 | |
b) Completed contract method | |||
Gross Profit recognized in 2017 | 0 | ||
Gross Profit recognized in 2018 | 0 | ||
Loss Profit recognized in 2019 | -1,50,000 |
Hi mate, |
I would be grateful to you if you can provide a thumbs up and write one beautiful comment. It will improve my rating and let me continue my journey here. |
In case of doubt, please comment. I will consider myself fortunate if I can help you. |
All the best for your bright future. |
* (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted...
(Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...
*P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...
On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Crane estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. Contract costs incurred to date Estimated...
Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Cullumber estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...
Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sunland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...
On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: 2020 2021 2022 Contract costs incurred during the year $2,700,600 $2,503,700 $2,125,700 Estimated costs to complete the contract at 12/31 3,729,400 2,125,700 –0– Billings...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $ 1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At...
On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...
On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...
Problem 18-11 On July 1, 2017, Sheffield Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Sheffield estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 $273,600 1,246,400...