Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company Inc. contracted to2020 TCosts to date (12/31/20) 270000 TEstimated Costs to Complete 1230000 T Estimated Total Costs 1500000 T Percent CompleteT Total Profit/Loss TGross Profit Recognized in 2020 | Profit/ (Loss) Recognized in 2021 | 2022 TCosts to date (12/31/22) TEs(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

(a)

Description 12/31/20 12/31/21 12/31/22
Contract price $     19,20,000 $     19,20,000 $     19,20,000
Costs incurred to date $       2,70,000 $     12,72,600 $     21,21,000
Estimated costs to complete $     12,30,000 $       7,47,400 $                  -  
Estimated total costs $     15,00,000 $     20,20,000 $     21,21,000
Estimated Gross profit $       4,20,000 $ (1,00,000) $ (2,01,000)
Percentage completed( Costs incurred to date/Estimated total costs) 18% 63% 100%
Cumulative gross profit (Estimated gross profit*cost to date/estimated total costs) $          75,600 $         -63,000 $      -2,01,000
Gross profit $          75,600 $      -1,38,600 $      -1,38,000
2021
Costs incurred to date $12,72,600
Estimated costs to complete $ 7,47,400
Estimated total costs $20,20,000
Contract price $19,20,000
Total profit/loss $        -63,000
Gross Profit recognised in 2020 $          75,600
Gross Profit recognised in 2021 $     -1,38,600
2022
Costs incurred to date $21,21,000
Estimated costs to complete $             -  
Estimated total costs $21,21,000
Contract price $19,20,000
Total profit/loss $     -2,01,000
Profit/(Loss) recognised in 2021 $     -1,38,600
Gross Profit/(Loss) recognised in 2020 $          75,600
Profit/(Loss) recognised in 2022 $     -1,38,000

(b)

Under completed contract method revenue and expenses are recognized at the end of the contract. Expenses incurred are recorded as construction in progress and progressive billings are recorded as liability.

Description 12/31/20 12/31/21 12/31/22
Costs incurred to date $       2,70,000 $     12,72,600 $     21,21,000
Contract price $     19,20,000 $     19,20,000 $     19,20,000
Revenue                              -                                -   $     19,20,000
Expense                              -                                -   $     21,21,000
Total profit/(loss) on contract                              -                                -   $      -2,01,000
Add a comment
Know the answer?
Add Answer to:
Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sunland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

  • On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel...

    On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Crane estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. Contract costs incurred to date Estimated...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2017, Coronado Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2017, Coronado Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Coronado estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017,...

  • On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: 2020 2021 2022 Contract costs incurred during the year $2,700,600 $2,503,700 $2,125,700 Estimated costs to complete the contract at 12/31 3,729,400 2,125,700 –0– Billings...

  • Problem 18-11 On July 1, 2017, Sheffield Construction Company Inc. contracted to build an office building...

    Problem 18-11 On July 1, 2017, Sheffield Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Sheffield estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 $273,600 1,246,400...

  • *P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020,...

    *P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...

    On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $ 1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At...

  • * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted...

    * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022:...

  • Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January...

    Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January 1, 2017. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract price for construction of the facility is $6,000,000. During the year, Yanmei incurred $1,185,800 in construction costs related to the construction...

  • (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a...

    (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT