Question

Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company...

Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sunland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. At 12/31/20 At 12/31/21 At 12/31/22 Contract costs incurred to date $327,800 $1,233,800 $2,092,700 Estimated costs to complete the contract 1,162,200 756,200 –0– Billings to Gumbel 310,000 1,100,000 1,840,000 (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank. If an amount should be deducted then enter the amount using either a negative sign prececeding the number e.g. -45 or parenthesis e.g. (45).) 2020 $ $ % $ $ 2021 $ $ $ $ 2022 $ $ $ $ $ (b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. If an amount should be deducted then enter the amount using either a negative sign prececeding the number e.g. -45 or parenthesis e.g. (45).) 2021 $ 2022 $ $

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer is given below

Gross Profit recognised in 2020 Gross Profit recognised in 2021 Gross Profit recognised in 2022 $85,800 $154,000 -$144,500 %

Add a comment
Know the answer?
Add Answer to:
Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Cullumber estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

  • On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel...

    On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Crane estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. Contract costs incurred to date Estimated...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2017, Coronado Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2017, Coronado Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Coronado estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017,...

  • Problem 18-11 On July 1, 2017, Sheffield Construction Company Inc. contracted to build an office building...

    Problem 18-11 On July 1, 2017, Sheffield Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Sheffield estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 $273,600 1,246,400...

  • *P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020,...

    *P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...

    On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $ 1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At...

  • (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a...

    (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...

  • Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January...

    Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January 1, 2017. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract price for construction of the facility is $6,000,000. During the year, Yanmei incurred $1,185,800 in construction costs related to the construction...

  • * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted...

    * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022:...

  • On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: 2020 2021 2022 Contract costs incurred during the year $2,700,600 $2,503,700 $2,125,700 Estimated costs to complete the contract at 12/31 3,729,400 2,125,700 –0– Billings...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT