Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January 1, 2017. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract price for construction of the facility is $6,000,000. During the year, Yanmei incurred $1,185,800 in construction costs related to the construction project. The estimated cost to complete the contract is $4,204,200. Lundquist Corp. was billed and paid 25% of the contract price. Prepare schedules to compute the amount of gross profit to be recognized for the year ended December 31, 2017, and the amount to be shown as costs and recognized profit in excess of billings or billings in excess of costs and recognized profit at December 31, 2017, under each of the following methods. (Enter negative amounts using either a negative sign preceding the number e.g.-45 or parentheses e.g. (45). If answer is o, please enter 0. Do not leave any fields blank.) (a) Completed-contract method. Gross Profit to be recognized Computation of Billings on Uncompleted Contract in Excess of Related Costs under Completed-Contract Method Construction Costs Incurred During the Year 1185800 Partial Billings on Contract 1500000 (314200) (b) Percentage-of-completion method

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Completed Contract Method

Gross Profit to be recognized

Profit should not be recognized before completion of project

Construction Costs Incurred during the Year

1,185,800

Partial Billings on contract: 6,000,000 * 25%

-1,500,000

Billings on uncompleted contract in excess of related cost

-314,200

Percentage-of Completion Method

Contract Price

6,000,000

Estimated total cost : (1,185,800 + 4,204,200)

-5,390,000

Estimated Total Gross Profit from Contract

$ 610,000

Percentage of Completion

(1,185,800 /5,390,000)

22%

Gross Profit to be recognized during the year: 610,000 * 22%

$ 134,200

Add a comment
Know the answer?
Add Answer to:
Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • intermediate accounting 14edition #17

    (Recognition of Profit and Balance Sheet Amounts for Long-Term Contracts)Yanmei Construction Company began operations January 1, 2012. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct amanufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract pricefor construction of the facility is $8,520,000. During the year, Yanmei incurred $1,683,836 in construction costs related to the construction project. Theestimated cost...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Cullumber estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sunland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2017, Coronado Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2017, Coronado Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Coronado estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017,...

  • Teal Construction Company began operations on January 1, 2017. During the year, Teal Construc t ed...

    Teal Construction Company began operations on January 1, 2017. During the year, Teal Construc t ed to complete the total cost of 1,500,000. The total contract price for construction of the days cost to complete the correct is $4,264 40 Land Corp was bed and paid of the contract price with LundstCorp to construct a minut e tot Acthat time. Talestined that it would take 5 years 1000 During the war, Tattored $1.1325 in construction costs related to the construction...

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to...

    Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows:...

  • Problem 18-10 On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for...

    Problem 18-10 On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,340,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2019 2018 $2,811,600 $2,152,400 $2,336,000 2,336,000 Contract costs incurred during the year Estimated costs to complete the contract at3,578,400 12/31 Billings...

  • Problem 18-10 On March 1, 2017, Culver Construction Company contracted to construct a factory building for Fabrik Manuf...

    Problem 18-10 On March 1, 2017, Culver Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2019 $1,962,900 Contract costs incurred during the year Estimated costs to complete the contract at 12/31 Billings to Fabrik during the year...

  • Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a...

    Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2022 $660,000 Costs to date Estimated costs to complete Progress billings to date (non-refundable) Cash collected to date 2020 $292,500 357,500 292,500 262,500 2021 $487,500 162,500...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT