Question

Teal Construction Company began operations on January 1, 2017. During the year, Teal Construc t ed to complete the total cost
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Please find below table useful to compute desired results: -

А 4540000 5963000 1133580 4264420 0.26 1 Particulars Given 2 Total Cost 3 Contract Price 4 Construction cost 5 Estimated Cost

End results would be as follows: -

Particulars Given 1 2 3 4 5 6 Total Cost Contract Price Construction cost Estimated Cost %age billed and paid 4.540.000 5.963

Add a comment
Know the answer?
Add Answer to:
Teal Construction Company began operations on January 1, 2017. During the year, Teal Construc t ed...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January...

    Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January 1, 2017. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract price for construction of the facility is $6,000,000. During the year, Yanmei incurred $1,185,800 in construction costs related to the construction...

  • Headland Construction Company began work on a $419,400 construction contract in 2017. During 2017, Headland incurred...

    Headland Construction Company began work on a $419,400 construction contract in 2017. During 2017, Headland incurred costs of $280,200, billed its customer for $216,300 and collected $174,500. At December 31, 2017, the estimated additional costs to complete the project total $161,600. Prepare Headland's journal entry to record proft or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • Prachce Problem 9 In Year 1, Amber Construction Corporation began construction work under a three-year contract....

    Prachce Problem 9 In Year 1, Amber Construction Corporation began construction work under a three-year contract. The contract price is $1,610,000. Long uses the percentage-of-completion method for financial reporting purposes. The financial statement presentation relating to this contract at December 31, year 1, is as follows: Balance Sheet $30,000 Accounts receivable (from construction progress billings) Construction in progress Less: Billings on Construction Contract $100,000 (93,000) 7,000 Cost of uncompleted contracts in excess of billings Income Statement $24,000 Income (before tax)...

  • Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started...

    Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:                                             2017                                    2018 Current year construction costs                                       $3,300,000                             $ 620,000 Estimated remaining costs to complete                              600,000                                   -0- Current year billings                                                            3,100,000                              1,400,000 Current year collections                                                    3,000,000                                1,500,000 Required: Calculate the following amounts for each method:               Completed Percentage-of Contract Completion                                   2017      2018    2017    2018 a) Gross Profit                                                                                              $             $           $          ...

  • 1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport...

    1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...

  • Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred...

    Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred costs of $279,500, billed its customer for $204,500, and collected $170,500. At December 31, 2020, the estimated additional costs to complete the project total $150,500. Prepare Cheyenne’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...

  • Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimated that the complex will take 3 years to construct. Additional information follows. Estimated cost of complex Contract price AA 600,000 900,000 The following data pertain to the construction period. 2019 610,000 $ 6100 A 2017 270,000 330,000 270,000 240,000 2018 450,000 150,000 550,000 500,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $...

  • Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred...

    Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Coronado’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.

  • Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $895,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $268,200 $482,760 $605,000 Estimated costs to complete 327,800 113,240 –0– Progress billings to date 267,000 552,000 895,000 Cash collected to date...

  • Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $246,000 354,000 270,000 240,000 2018 $432,000 168,000 546,000 496,000 2019 $612,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT