intermediate accounting 14edition #17

(Recognition of Profit and Balance Sheet Amounts for Long-Term Contracts)
Yanmei Construction Company began operations January 1, 2012. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct amanufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract pricefor construction of the facility is $8,520,000. During the year, Yanmei incurred $1,683,836 in construction costs related to the construction project. Theestimated cost to complete the contract is $5,969,964. Lundquist Corp. was billed and paid 30% of the contract price.

Prepare schedules to compute the amount of gross profit to be recognized for the year ended December 31, 2012, and the amount to be shown as "cost and recognizedprofit on uncompleted contract in excess of related billings" or "billings on uncompleted contract in excess of related costs and recognized profit" at December31, 2012, under each of the following methods. (If answer is zero, please enter 0, do not leave any fields blank. For negative numbers use either a negative signpreceding the number, e.g. -45 or parenthesis, e.g. (45).)

a)completed-contract method

b) percentage of completion method

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
EXERCISE 18-17 (a) Computation of Gross Profit to Be Recognized under Completed- Contract Method. No computation necessary. No gross profit to be recognized prior to completion of contract. Computation of Billings on Uncompleted Contract in Excess of Related Costs under Completed-Contract Method. Construction costs incurred during the year...................... $ 1,185,800 Partial billings on contract (25% X $6,000,000) .................. (1,500,000) $ (314,200) 18-28 Copyright
Add a comment
Know the answer?
Add Answer to:
intermediate accounting 14edition #17
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January...

    Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January 1, 2017. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract price for construction of the facility is $6,000,000. During the year, Yanmei incurred $1,185,800 in construction costs related to the construction...

  • Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to...

    Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows:...

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Cullumber estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sunland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

  • Teal Construction Company began operations on January 1, 2017. During the year, Teal Construc t ed...

    Teal Construction Company began operations on January 1, 2017. During the year, Teal Construc t ed to complete the total cost of 1,500,000. The total contract price for construction of the days cost to complete the correct is $4,264 40 Land Corp was bed and paid of the contract price with LundstCorp to construct a minut e tot Acthat time. Talestined that it would take 5 years 1000 During the war, Tattored $1.1325 in construction costs related to the construction...

  • Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a...

    Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2022 $660,000 Costs to date Estimated costs to complete Progress billings to date (non-refundable) Cash collected to date 2020 $292,500 357,500 292,500 262,500 2021 $487,500 162,500...

  • Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...

    Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10−20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...

  • McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...

    McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2023 and completed in 2024. Cost and other data are presented below: 2024 $1,300 Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2023 $1,500 1,200 1,200 1,000 1,300 1,500 1. Compute the amount of revenue and gross profit recognized during 2023 and 2024. 2. Assume that McCombs recognizes revenue on this contract over...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT