Problem 18-10 On March 1, 2017, Culver Construction Company contracted to construct a factory building for Fabrik Manufacturi2018 2019 (b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a resu2017 2018 2019 LINK TO TEXT Question Attempts: 0 of 3 used SAVE FOR LATER SUBMIT ANSWER

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer :

Given data is :

Total contract price = $ 8,450,000

a)From the given data :

Particulars 2017 2018 2019
Cost in present year 3,052,800 2,254,300 1,962,900
Total cost 3,052,800

= 3,052,800 + 2,254,300

= 5,307,100

= 5,307,100 + 1,962,900

= 7,270,000

Estimated cost 3,307,200 1,962,900 0
Total estimated cost 6,360,000

= 5,307,100 + 1,962,900

= 7,270,000

7,270,000
Percentage of completion = (cost incurred till date(Total cost) / total estimated cost)

= 3,052,800 / 6,360,000

= 0.48

= 48%

= 5,307,100 / 7,270,000

= 0.73

= 73%

= 7,270,000 / 7,270,000

= 1

= 100%

Total revenue $ 8,450,000 $ 8,450,000 $ 8,450,000
Recognized revenue total

=8,450,000 * 48%

= 4,056,000

= 8,450,000 * 73%

= 6,168,500

= 8,450,000 * 1

= 8,450,000

Recognized revenue in past year 0 4,056,000 6,168,500
Recognized revenue in present year 4,056,000

= 6,168,500 - 4,056,000

= 2,112,500

2,281,500

b)Using completed contract method :

Particulars 2017 2018 2019
Revenue in present year 4,056,000 2,112,500 2,281,500
Total cost in present year 3,052,800 2,254,300 1,962,900
Gross Profit

= 4,056,000 - 3,052,800

= 1,003,200

= 2,112,50- 2,254,300

= - 141,800

= 2,281,500 - 1,962,900

= 318,600

Add a comment
Know the answer?
Add Answer to:
Problem 18-10 On March 1, 2017, Culver Construction Company contracted to construct a factory building for Fabrik Manuf...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On March 1, 2017, Larkspur Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2017, Larkspur Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,052,800 $2,254,300 $1,962,900 Estimated costs to complete the contract at 12/31 3,307,200 1,962,900 –0– Billings...

  • On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...

  • On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabr...

    On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...

  • Problem 18-10 On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for...

    Problem 18-10 On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,340,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2019 2018 $2,811,600 $2,152,400 $2,336,000 2,336,000 Contract costs incurred during the year Estimated costs to complete the contract at3,578,400 12/31 Billings...

  • CALCULATOR PRINTER VERSION BACK Problem 18-10 On March 1, 2017, Riverbed Construction Company contracted to construct...

    CALCULATOR PRINTER VERSION BACK Problem 18-10 On March 1, 2017, Riverbed Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,490,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,907,000 $2,465,800 $1,987,200 Estimated costs to complete the contract...

  • On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: 2020 2021 2022 Contract costs incurred during the year $2,700,600 $2,503,700 $2,125,700 Estimated costs to complete the contract at 12/31 3,729,400 2,125,700 –0– Billings...

  • Problem 18-11 On July 1, 2017, Sheffield Construction Company Inc. contracted to build an office building...

    Problem 18-11 On July 1, 2017, Sheffield Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Sheffield estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 $273,600 1,246,400...

  • On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...

    On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $ 1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2017, Coronado Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2017, Coronado Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Coronado estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017,...

  • (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a...

    (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT