Answer :
Given data is :
Total contract price = $ 8,450,000
a)From the given data :
Particulars | 2017 | 2018 | 2019 |
Cost in present year | 3,052,800 | 2,254,300 | 1,962,900 |
Total cost | 3,052,800 |
= 3,052,800 + 2,254,300 = 5,307,100 |
= 5,307,100 + 1,962,900 = 7,270,000 |
Estimated cost | 3,307,200 | 1,962,900 | 0 |
Total estimated cost | 6,360,000 |
= 5,307,100 + 1,962,900 = 7,270,000 |
7,270,000 |
Percentage of completion = (cost incurred till date(Total cost) / total estimated cost) |
= 3,052,800 / 6,360,000 = 0.48 = 48% |
= 5,307,100 / 7,270,000 = 0.73 = 73% |
= 7,270,000 / 7,270,000 = 1 = 100% |
Total revenue | $ 8,450,000 | $ 8,450,000 | $ 8,450,000 |
Recognized revenue total |
=8,450,000 * 48% = 4,056,000 |
= 8,450,000 * 73% = 6,168,500 |
= 8,450,000 * 1 = 8,450,000 |
Recognized revenue in past year | 0 | 4,056,000 | 6,168,500 |
Recognized revenue in present year | 4,056,000 |
= 6,168,500 - 4,056,000 = 2,112,500 |
2,281,500 |
b)Using completed contract method :
Particulars | 2017 | 2018 | 2019 |
Revenue in present year | 4,056,000 | 2,112,500 | 2,281,500 |
Total cost in present year | 3,052,800 | 2,254,300 | 1,962,900 |
Gross Profit |
= 4,056,000 - 3,052,800 = 1,003,200 |
= 2,112,50- 2,254,300 = - 141,800 |
= 2,281,500 - 1,962,900 = 318,600 |
Problem 18-10 On March 1, 2017, Culver Construction Company contracted to construct a factory building for Fabrik Manuf...
On March 1, 2017, Larkspur
Construction Company contracted to construct a factory building for
Fabrik Manufacturing Inc. for a total contract price of $8,450,000.
The building was completed by October 31, 2019. The annual contract
costs incurred, estimated costs to complete the contract, and
accumulated billings to Fabrik for 2017, 2018, and 2019 are given
below: 2017 2018 2019 Contract costs incurred during the year
$3,052,800 $2,254,300 $1,962,900 Estimated costs to complete the
contract at 12/31 3,307,200 1,962,900 –0– Billings...
On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...
On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...
Problem 18-10 On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,340,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2019 2018 $2,811,600 $2,152,400 $2,336,000 2,336,000 Contract costs incurred during the year Estimated costs to complete the contract at3,578,400 12/31 Billings...
CALCULATOR PRINTER VERSION BACK Problem 18-10 On March 1, 2017, Riverbed Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,490,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,907,000 $2,465,800 $1,987,200 Estimated costs to complete the contract...
On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: 2020 2021 2022 Contract costs incurred during the year $2,700,600 $2,503,700 $2,125,700 Estimated costs to complete the contract at 12/31 3,729,400 2,125,700 –0– Billings...
Problem 18-11 On July 1, 2017, Sheffield Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Sheffield estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 $273,600 1,246,400...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $ 1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At...
Problem 18-11
Your answer is partially correct. Try again.
On July 1, 2017, Coronado Construction Company Inc. contracted
to build an office building for Gumbel Corp. for a total contract
price of $1,880,000. On July 1, Coronado estimated that it would
take between 2 and 3 years to complete the building. On December
31, 2019, the building was deemed substantially completed.
Following are accumulated contract costs incurred, estimated costs
to complete the contract, and accumulated billings to Gumbel for
2017,...
(Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...