Question

On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing...

On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below:

2020

2021

2022

Contract costs incurred during the year $2,700,600 $2,503,700 $2,125,700
Estimated costs to complete the contract at 12/31 3,729,400 2,125,700 –0–
Billings to Fabrik during the year 3,230,000 3,470,000 1,700,000


(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

2020

                                                          Profit / (Loss) Recognized in 2020Estimated Total CostsCosts IncurredPercent CompleteRevenue RecognizedCosts to date (12/31/20)Estimated Costs to Complete

$

                                                          Costs IncurredCosts to date (12/31/20)Revenue RecognizedEstimated Total CostsPercent CompleteEstimated Costs to CompleteProfit / (Loss) Recognized in 2020
                                                          Profit / (Loss) Recognized in 2020Revenue RecognizedEstimated Costs to CompleteEstimated Total CostsCosts to date (12/31/20)Percent CompleteCosts Incurred

$

                                                          Estimated Total CostsPercent CompleteCosts IncurredEstimated Costs to CompleteProfit / (Loss) Recognized in 2020Costs to date (12/31/20)Revenue Recognized %
                                                          Profit / (Loss) Recognized in 2020Percent CompleteRevenue RecognizedEstimated Total CostsEstimated Costs to CompleteCosts to date (12/31/20)Costs Incurred

$

                                                          Revenue RecognizedEstimated Costs to CompleteProfit / (Loss) Recognized in 2020Estimated Total CostsCosts IncurredCosts to date (12/31/20)Percent Complete
                                                          Costs to date (12/31/20)Costs IncurredPercent CompleteEstimated Costs to CompleteProfit / (Loss) Recognized in 2020Revenue RecognizedEstimated Total Costs

$

2021

                                                          Profit / (Loss) Recognized in 2020Revenue Recognized in 2021Percent CompleteCosts to date (12/31/21)Estimated Total CostsEstimated Costs to CompleteCosts Incurred in 2021

$

                                                          Estimated Total CostsCosts to date (12/31/21)Revenue Recognized in 2021Costs Incurred in 2021Estimated Costs to CompleteProfit / (Loss) Recognized in 2020Percent Complete
                                                          Profit / (Loss) Recognized in 2020Estimated Total CostsEstimated Costs to CompleteCosts to date (12/31/21)Costs Incurred in 2021Percent CompleteRevenue Recognized in 2021

$

                                                          Profit / (Loss) Recognized in 2020Estimated Total CostsEstimated Costs to CompleteCosts Incurred in 2021Revenue Recognized in 2021Costs to date (12/31/21)Percent Complete %
                                                          Costs Incurred in 2021Revenue Recognized in 2021Estimated Costs to CompleteCosts to date (12/31/21)Estimated Total CostsPercent CompleteProfit / (Loss) Recognized in 2020

$

                                                          Estimated Costs to CompleteCosts to date (12/31/21)Estimated Total CostsRevenue Recognized in 2021Percent CompleteCosts Incurred in 2021Profit / (Loss) Recognized in 2020
                                                          Costs Incurred in 2021Percent CompleteEstimated Total CostsEstimated Costs to CompleteCosts to date (12/31/21)Profit / (Loss) Recognized in 2021Revenue Recognized

$

2022

                                                          Profit Previously RecognizedProfit / (Loss) Recognized in 2022Total Revenue RecognizedTotal Costs IncurredTotal Profit on Contract

$

                                                          Total Costs IncurredTotal Profit on ContractProfit Previously RecognizedProfit / (Loss) Recognized in 2022Total Revenue Recognized
                                                          Total Profit on ContractProfit Previously RecognizedProfit / (Loss) Recognized in 2022Total Revenue RecognizedTotal Costs Incurred
                                                          AddLess:                                                           Total Profit on ContractTotal Costs IncurredProfit Previously RecognizedProfit / (Loss) Recognized in 2022Total Revenue Recognized
                                                          Total Costs IncurredProfit Previously RecognizedTotal Revenue RecognizedTotal Profit on ContractProfit / (Loss) Recognized in 2022

$


(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

2020: 2021: 2022:

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a) The percentage of completion method is used for longer-term projects and recognizes revenue and expenses as a percentage of the project’s completion during the period. Computation of Gross profit recognized in different years will be as follows:

Amount in $ 2022 Particulars 2020 2021 A 2,700,600 2,125,700 5,204,300 B Cost incurred during the year Cost incurred during p

2. The completed contract method is an method that postpones the reporting of income and expenses, till a contract is completed. Hence, all the profit of the contract will be recognized in the year in which it is completed:

Hence, all the revenue will be recognized in the Year 2022.

Gross Profit to be recognized in Year 2022 = Total Revenue - Total Expenses

Gross Profit to be recognized in Year 2022 = $8,400,000 - ($2,700,600 + $2,503,700 + $2,125,700) = $1,070,000

Gross Profit to be recognized in Year 2020 & 2021 = 0

Add a comment
Know the answer?
Add Answer to:
On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...

  • On March 1, 2017, Larkspur Construction Company contracted to construct a factory building for Fabrik Manufacturing...

    On March 1, 2017, Larkspur Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,052,800 $2,254,300 $1,962,900 Estimated costs to complete the contract at 12/31 3,307,200 1,962,900 –0– Billings...

  • Problem 18-10 On March 1, 2017, Culver Construction Company contracted to construct a factory building for Fabrik Manuf...

    Problem 18-10 On March 1, 2017, Culver Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2019 $1,962,900 Contract costs incurred during the year Estimated costs to complete the contract at 12/31 Billings to Fabrik during the year...

  • On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabr...

    On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...

  • On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel...

    On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Crane estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. Contract costs incurred to date Estimated...

  • Problem 18-10 On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for...

    Problem 18-10 On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,340,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2019 2018 $2,811,600 $2,152,400 $2,336,000 2,336,000 Contract costs incurred during the year Estimated costs to complete the contract at3,578,400 12/31 Billings...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Cullumber estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

  • (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a...

    (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...

  • * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted...

    * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022:...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Sunland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sunland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT