Question

Which of the following statements is correct? (a) The NPV profile graph for a normal project...

Which of the following statements is correct?
(a) The NPV profile graph for a normal project will generally have a postive(upward) slope as the life of the project increase.
(b) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life
(c) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firms value varies with the cost of capital
(d) We cannot draw a project's NPV profile unless we know the appropriate WACC for use in evaluating the project's NPV
(e) An NPV profile graph shows how a projects payback varies as the cost of capital changes

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct answer is option C i.e. An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firms value varies with the cost of capital.

NPV profile of a project or investment is a graph of the project's NPV corresponding to different values of discount rates.

For further clarrification please comment.

Thumbs up Please!. Thank You.

Add a comment
Know the answer?
Add Answer to:
Which of the following statements is correct? (a) The NPV profile graph for a normal project...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Which of the following statements is CORRECT? The internal rate of return method (IRR) is generally...

    Which of the following statements is CORRECT? The internal rate of return method (IRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects. The discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects. The payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects. The net present value method (NPV) is generally regarded by academics...

  • A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the...

    A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's Select (where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the Select of the differences in the projects' cash flows (Project Delta). A Select NPV profile indicates that increases in the cost of capital...

  • Comparing the NPV profile of an investment project to that of a financing project demonstrates why...

    Comparing the NPV profile of an investment project to that of a financing project demonstrates why the: a. incremental IRR varies with changes in the market rate of interest. b. IRR decision rule for investment projects is the opposite of the rule for financing projects. c. life span of a project affects the decision as to which project to accept. d. NPV rule for financing projects is the opposite of the rule for investment projects. e. profitability index and the...

  • Dropdown options: (accept, reject), (accept, reject), (IRR, WACC) An NPV profile plots a project's NPV at...

    Dropdown options: (accept, reject), (accept, reject), (IRR, WACC) An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile is shown in the graph. Identify the range of costs of capital that a firm would use to accept and reject this project by responding to the drop-down choices below the graph. NPV (Dollars) A -200 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) B The point at which...

  • s. Understanding the NPV profile Aa Aa If an independent project with conventional, or normal, cash flows is being...

    s. Understanding the NPV profile Aa Aa If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects W and X are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) Year Project W Project x 800 0 - $1,500 -$1,000 $200 $350 600 Project X 2 $350 $500 $400 $600 400 4 $600 $750 Project W 200...

  • 5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled...

    5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled "A" and "B" in the graph. A project's NPV profile is shown as follows. Identify the range of costs (ranges labeled "A" and "B") of capital that a firm would use to accept and reject this project. NPV (Dollars) -200 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) True or False: The NPV and IRR methods can...

  • 5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled "A" and "B" in the graph. A p...

    5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled "A" and "B" in the graph. A project's NPV profile is shown as follows. Identify the range of costs (ranges labeled "A" and "B") of capital that a firm would use to accept and reject this project. NPV (Dollars) 400 А -200 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) The point at which the NPV profile...

  • Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with...

    Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The longer a project's payback period, the more desirable the project is normally considered to be by this criterion. b. One drawback of the payback criterion for evaluating projects is that this method does not properly account for the time value of money. c. If a project's payback is positive, then the project...

  • < Back to Assignment Do No Harm: /2 Attempts: 5. NPV profiles An NPV profile plots...

    < Back to Assignment Do No Harm: /2 Attempts: 5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled "A" and "B" in the graph. A project's NPV profile is shown as follows. Identify the range of costs (ranges labeled "A" and "B") of capital that a firm would use to accept and reject this project NPV (Dollars) 400 300 A 200 100 0 -100 200 0 2 4 6 8 10 12 14...

  • Which of the following statements is CORRECT? A) The NPV method is regarded by most academics...

    Which of the following statements is CORRECT? A) The NPV method is regarded by most academics as being the best indicator of a project's profitability, hence most academics recommend that firms use only this one method and disregard other methods. B) The NPV method was once the favorite of academics and business executives, but today most authorities regard the MIRR as being the best indicator of a project's profitability. C) A project's NPV depends on the total amount of cash...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT