Can a project have negative cash flows for the first few years before having positive cash flows? Explain your answer
Positive cash flow is when a company has more cash left after all the expenses are paid out whereas negative cash flow is when cash is paid out more than it is receiving.
Yes, in my opinion, a project can have negative cash flows for the first few years before having some positive cash flows. In case of negative cash flows in a project, a company can't reinvest the cash into the project. Negative cash flows can also indicate an investment for long term success rather than actually getting some earnings.
Hope this helps :)
Can a project have negative cash flows for the first few years before having positive cash...
A) A project that provides annual cash flows of $14369 for eight years costs $77894 today. What is the NPV for the project if the required return is 7 percent? (Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places. (e.g., 32.16)) B) A project that provides annual cash flows of $17545 for eight years costs $75634 today. What is the NPV for the project if the required return is 19 percent? (Negative amount...
Which of the following statements is CORRECT? a. If a project has normal cash flows, then its IRR must be positive. b. If a project has normal cash flows, then its MIRR must be positive. c. If a project has normal cash flows, then it can have two NPVs. d. If a project has normal cash flows, then it can have two IRRs. e. If a project has normal cash flows, then it cannot have two IRRs. vi. Which of...
A project that provides annual cash flows of $14369 for eight years costs $77894 today. What is the NPV for the project if the required return is 7 percent? (Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places. (e.g., 32.16)) A project that provides annual cash flows of $17545 for eight years costs $75634 today. What is the NPV for the project if the required return is 19 percent? (Negative amount should be...
1. You have the chance to participate in a project that produces the following cash flows: Cash Flows ($) C0 C1 C2 4,600 4,400 –10,800 a. The internal rate of return is 12.69%. If the opportunity cost of capital is 12%, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.) NPV $ __________. 2. Consider the following projects: Cash Flows...
You are evaluating a project that will cost $493,000, but is expected to produce cash flows of $128,000 per year for 10 years, with the first cash flow in one year. Your cost of capital is 11.3% and your companys preferred payback period is three years or less. a. What is the payback period of this project? b. Should you take the project if you want to increase the value of the company? If you want to increase the value...
You have the chance to participate in a project that produces the following cash flows: Cash Flows ($) C0 C1 C2 –5,000 4,000 –11,000 a. The internal rate of return is 13%. If the opportunity cost of capital is 10%, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to the nearest whole number.) NPV: ________
There is a project whose cash flows are shown below. Before the investor decided to accept or reject the project, interest rates are changed, and thus, the cost of capital (r) is also changed. The change in the interest rate did not affect the forecasted cash flows. By how much did the change in the r affect the project's forecasted NPV? Note that a project's expected NPV can be negative, in which case it should be rejected. Old r: 8.00%...
A project requires, as its only cost, an initial investment of
$17,000. It then generates positive future cash flows. The
appropriate discount rate is 22%. This project has an NPV of -$935
(negative NPV). What can you say about this project’s IRR?
A project requires, as its only cost, an initial investment of $17,000. It then generates positive future cash flows. The appropriate discount rate is 22%. This project has an NPV of -$935 (negative NPV). What can you say...
In their early years, start-up companies are most likely to report: A. Positive cash flows from both operating activities and investing activities B. Negative cash flows from operating activities and positive cash flows from investing activities C. Positive cash flows from financing activities and negative cash flows from investing activities D. Negative cash flows from financing activities and positive cash flows from operating activities E. Negative cash flows from both financing activities and operating activities
Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 1 2 3 4 1,250 3,500 - 6,000 - 2,000 - 6,000 1,250 2,000 1,250 +3,500 5,500 2,500 1,250 3,500 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a cutoff period of 3 years, which projects will you accept? d-1....