Question

There is a project whose cash flows are shown below. Before the investor decided to accept...

There is a project whose cash flows are shown below.

  • Before the investor decided to accept or reject the project, interest rates are changed, and thus, the cost of capital (r) is also changed.
  • The change in the interest rate did not affect the forecasted cash flows.
  • By how much did the change in the r affect the project's forecasted NPV?
  • Note that a project's expected NPV can be negative, in which case it should be rejected.

Old r:

8.00%

New r:

11.25%

Year

0

1

2

3

Cash flows

−$1,000

$410

$410

$410

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Project
Discount rate 0.08
Year 0 1 2 3
Cash flow stream -1000 410 410 410
Discounting factor 1 1.08 1.1664 1.259712
Discounted cash flows project -1000 379.6296 351.5089 325.4712
NPV = Sum of discounted cash flows
NPV Project = 56.61
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project
Discount rate 0.1125
Year 0 1 2 3
Cash flow stream -1000 410 410 410
Discounting factor 1 1.1125 1.237656 1.376893
Discounted cash flows project -1000 368.5393 331.2713 297.772
NPV = Sum of discounted cash flows
NPV Project = -2.42
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

Change in NPV = 56.61-(-2.42) = 59.03

NPV decreased by 59.03

Add a comment
Know the answer?
Add Answer to:
There is a project whose cash flows are shown below. Before the investor decided to accept...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1) Last month, Standard Systems analyzed the project whose cash flows are shown below. However, before...

    1) Last month, Standard Systems analyzed the project whose cash flows are shown below. However, before the decision to accept or reject the project took place, the Federal Reserve changed interest rates and therefore the firm's cost of capital (r). The Fed's action did not affect the forecasted cash flows. By how much did the change in the r affect the project's forecasted NPV? Note that a project's expected NPV can be negative, in which case it should be rejected....

  • Rivoli Inc. hired you as a consultant to help estimate its cost of capital. You have...

    Rivoli Inc. hired you as a consultant to help estimate its cost of capital. You have been provided with the following data: D0 = $0.80; P0 = $77.50; and g = 8.00% (constant). Based on the DCF approach, what is the cost of equity from retained earnings? Group of answer choices 8.66% 7.20% 10.12% 9.11% 10.30% Malholtra Inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Note that a project's...

  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively Time Cash Flow 0 1 2 3 4 5 6 -1,150 30570770770 370770 Use the NPV decision rule to evaluate this project, should it be accepted or rejected? Multiple Choice 0...

  • Compute the MIRR statistic for Project I and note whether to accept or reject the project...

    Compute the MIRR statistic for Project I and note whether to accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 15 percent. Project I Time 0 1 2 3 4 5 Cash Flow –$ 1,000 $ 400 $ 300 $ 200 $ 300 $ 50 Multiple Choice The project's MIRR is 18.19 percent and the project should be accepted. The project's MIRR is 12.67 percent and the project should be...

  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively.   Time 0 1 2 3 4 5 6   Cash Flow -1,040 140 460 660 660 260 660 Use the NPV decision rule to evaluate this project; should it be accepted or...

  • Compute the PI statistic for Project Z and advise the firmwhether to accept or reject...

    Compute the PI statistic for Project Z and advise the firm whether to accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 10 percent.Project ZTime012345Cash Flow–$1,000$350$380$420$300$100Multiple ChoiceThe project's PI is 8.48 percent and the project should be rejected.The project's PI is 16.48 percent and the project should be accepted.The project's PI is 21.48 percent and the project should be accepted.The project's PI is 8.48 percent and the project should be...

  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively Time 0 1 4 5 6 Cash Flow -1,150 30 570 770 770 370 770 Use the discounted payback decision rule to evaluate this project; should it be accepted or rejected?...

  • Assume a project has normal cash flows. Given this, you should accept the project Multiple Choice...

    Assume a project has normal cash flows. Given this, you should accept the project Multiple Choice a) if the total cash inflows exceed the initial cash outflow. b) if, and only if, the NPV is exactly equal to zero. c) if the NPV is positive and reject it if the NPV is negative. d) only if the NPV is equal to the initial cash flow. e) because it has positive cash flows for every time period after the initial investment

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0123 Project -35,000 25,000 45,000 16,000 A Cash Flow Project -45,000 25,000 35,000 B Cash Flow Use the NPV decision rule to evaluate these projects; which one(s) should...

  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively Time 0 3 4 5 6 Cash Flow -1,040 140 460 660 660 260 660 Use the payback decision rule to evaluate this project; should it be accepted or rejected? Multiple...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT