Figure P3 shows the soil profile at a site for a proposed office building. It is...
[Problems 1-4] The soil profile at a site for a proposed office building consists of a layer of fine sand 10.4 m thick above a layer of soft, normally consolidated clay 2 m thick. Below the soft clay is a deposit of coarse sand. The groundwater table was observed at 3 m below ground level. The void ratio of the sand is 0.76, and the water content of the clay is 43%. The building will impose a vertical stress increase...
1. (25 points) The soil profile at a site consists of a layer of fine sand 5 m thick above a layer of clay 4 m thick. Below the clay is a layer of impermeable rock. The groundwater table was observed at 2 m below ground level. The unit weight of the sand above and below the water table is 20 KN/m'. The water content of the clay is 25% and its dry unit weight is 15 KN/m'. The compression...
geotechnical engineering The soil profile at a site consists of a clay layer 10 m thick, sandwich between two sand layers. The top sand layer has a density of 1.9 Mg/m² and is 5 m thick. Below this layer is a 10 m thick clay layer with a saturated density of 1.8 Mg/m' and a saturated water content 42%. The deeper sand layer has a saturated density of 1.9 Mg/m² and extend to the depth investigated at the site. The...
e3 shows the soil profile (sand-clay-sand) at the site of a warehouse that causes a surface ding of 100 kPa. (pw= 1000 kg/m; g 9.81 m/s2) on 4 (25 marks) A clay sample was cored at 7 m depth (middle of the clay layer). Based on laboratory test data, it was found that the clay was over-consolidated with OCR = 2.5 (before applying surface loading), compression index Ce 0.44 and recompression index C. = 0.1. The consolidation coefficient of clay...
In the figure below, the natural soil profile consists of sand overlying clay overlying sand overlying bedrock. A water table is present 1 m beneath the surface of the natural ground. If 4 m of consistent fill material (γfill = 15 kN/m3) was placed on top of this soil profile that covered a large area, determine: (a) The consolidation settlement of the clay layer (using 4 equal layers in your calculation), and (b) The time (in days) for this consolidation...
mblem No. 3 ( 30%) A steel eil tank with flexible foundation, 50m diameter and 12m height has oil y-9.42 kN The foundation soil is 3.3m of sand Ф.35° and Y-18.85 kNm' overlaying a layer of uniform. armally consolidated clay of 17tn thick with Ф-10° and Y-17.3 kN/m.c_ 12 kNtn.c -127 and C-04 underlain by another layer of sand. The water table is at the surface level. Oedometer test on a 2.54cm thick, doubly-drained sample from the clay stratum attained...
Problem 2. [2596] Figure 2 shows a soil profile. The uniformly distributed load on the ground surface is (1) Estimate the primary consolidation settlement of the clay layer due to the application of Ap. (2) If the clay layer is preconsolidated and the average preconsolidation pressure is 80 kPa, what will be the expected primary consolidation settlement if the recompression index is C 0.2 x Cc? p 87 kPa 1 m Dry Sand Sand: Saturated Sand Dry Unit weight: 14.6...
soil Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below, after 10 minutes 50% consolidation is reached . a) How long time in days would the same degree of consolidation(50%) be reached in the field ?. b) How much the Final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? 3m 2m Sand surcharge Y...
Question 5 (Effective Stress & Consolidation) Figure 05 shows the soil profile of a construction site. The water table is at the ground surface. Saturated unit weight of the sand is 18.8kN/m' and that of the clay is 19.6kN/m. Assume permeability of the clay is very low and unit weight of water is 10kN/m'. Water Table Sand 5m Clay 6m Figure 05 a) Determine the vertical total stress, pore water pressure, and vertical effective stress at the mid-height of the...
For the soil profile shown below, calculate the final settlement due to the placement of the sand fill. Estimate the excess pore pressure at a depth of 1.5 m into the third clay layer 1.5 years after the fill is placed. Assume the coefficient of consolidation is Cv = 1.8 m2/yr. Fill y = 16.0 kN/m² (3m thick) Clay 1 (3m thick) Sand (0.5m thick) Clay 2 (2m thick) Sand (0.5m thick) Clay 3 (4m thick) Sand (0.5m thick) eo...