Question

10-18 WACC and optimal capital budget Adams Corporation is considering four average-risk projects with the following costs an
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

  • Before tax cost of Debt (rd) = 5%

Tax rate = 30%

After Tax cost of Debt = Before tax cost of Debt*(1-tax rate)

= 5(1-0.30)

= 3.5%

  • Cost of Preferred Stock = Annual Dividends/Value of Preferred Stock
    = $5/$100
    = 5%
  • Cost of Equity = (D1/P0)+g
    = (5/40) + 0.05
    = 17.5%

2.).

WACC= (Weight of Debt)(Cost of Debt)+ (Weight of Preferred Stock)(Cost of Preferred Stock) (Weight of Equity)(Cost of Equity)

WACC = (0.40)(3.5%) + (0.10)(5%) + (0.50)(17.5%)

WACC = 1.4% + 0.50% + 8.75%

WACC = 10.65%

3). Project Adam should accept:-

Project Cost Expected rate of return WACC Return after WACC Amount of Return
1 $2000 50% 10.65% 39.35% $787
2 $3000 40% 10.65% 29.35% $880.5
3 $5000 30% 10.65% 19.35% $967.5
4 $2000 20% 10.65% 9.35% $187

Since, Project 3 provides better after amount of return on cost. Hence, Project 3 should be chosen.

Add a comment
Know the answer?
Add Answer to:
10-18 WACC and optimal capital budget Adams Corporation is considering four average-risk projects with the following...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT