Question

4. The following system delivers 40MW at 0.8 pf lagging to the grid at 110kV. In the middle of the line there is a zero resis

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Soln Taking 10.5kV; 250 MUA base at generator side. (i) calculating line reactance Xine = 0.2 x 50=100 Z Bare = (VBase) ² UbaIL (p = 0-2 /-cos (0.8) (IL (pu) = 0.2 [-36.87 pu) (iii) Calculating pre fault voltage L j0.1 pu | j0.1033 j0-10331. Ji (pu(10) calculating sub transient thevenin reactance cet fault point (replacing woltage source with short ect) jo.1 jo 1033 jo.1I = 1.012520.94 jo.0841 If = 12.0352 L-89.06 pu Fault current If I = 12.0352 pu Bare current SB IB = 3. VB fault current in a

Add a comment
Know the answer?
Add Answer to:
4. The following system delivers 40MW at 0.8 pf lagging to the grid at 110kV. In...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Zone 1 Zone 3 Zone 2 Xice j1002 BE SO MW 0.8 pf lagging Vload =...

    Zone 1 Zone 3 Zone 2 Xice j1002 BE SO MW 0.8 pf lagging Vload = 30 kV Ti 50 MVA 11/132 kV X= 10% Tz 50 MVA 132/33 kV X=12% Figure 1 2. A 500 MVA, 20 kV, 50 Hz synchronous generator with reactances Xd" = 0.15, Xá = 0.24, Xo = 1.1 p.u. and time constant To = 0.035, Tó' = 2.0, TA = 0.2 seconds is connected to a circuit breaker. The generator is operating at 5%...

  • Problem 2 (50 points): The synchronous generator shown in the figure below is operated at its rat...

    Problem 2 (50 points): The synchronous generator shown in the figure below is operated at its rated apparent power (100 MVA), 0.95 pf. lagging, and 5% above rated voltage. Determine the subtransient fault current if a three phase short circuit fault occurs at the terminal of the motor (Bus 2) T1 2 100 MVA 100 MVA 13.8 kV 13.8 kV Δ/138 kVY X" = 0.15 X = 0.10 100 MVA 138 kV Y/13.8 kV Δ X0.10 100 MVA 13.8 kV...

  • A 200-km, 230-kV, 60-Hz three-phase line has a positive-sequence series impedance ?=0.08+?0.48 Ω/km and a positive-sequence...

    A 200-km, 230-kV, 60-Hz three-phase line has a positive-sequence series impedance ?=0.08+?0.48 Ω/km and a positive-sequence shunt admittance ?=?3.33×10−6 S/km. At full load, the line delivers 250 MW at 0.99 pf lagging and at 220 kV. Using the nominal ? circuit, calculate: a. The ABCD parameters, b. The sending-end voltage and current, c. The percent voltage regulation.

  • QUESTIONS 1- A 69-kV, three-phase transmission line is 20 km long. The line has a per...

    QUESTIONS 1- A 69-kV, three-phase transmission line is 20 km long. The line has a per phase series impedance of 0,120 + 10,4325 per km. Detemine the sending end voltage, voltage regulation, the sending end power, and the transmission efficiency when the line delivers (a) 60 MVA, 0.8 lagging power factor at 60 kV. (b) 110 MW, unity power factor at 60 kV

  • Solution of two part please with steps Question 1: Ve-le The rating of s three phase...

    Solution of two part please with steps Question 1: Ve-le The rating of s three phase three winding transformer are: Y-connected un KV 40 MVA Y-connected 22 KV 40 MVA 4 KV 15 MVA Primary Secondary Tertiary A-connected Neglecting winding resistance and exciting current, the per unit leakage reactance are X 9.6 % pu on 40 MVA. 110/22 KV X7.2 % pu on 40 MVA, 110/ 4 KV Xg 12 % pu on 40 MVA, 22 4 KV a) Determine...

  • Problem 2 (50 points): The generator in the figure generates and delivers 150 MW to the...

    Problem 2 (50 points): The generator in the figure generates and delivers 150 MW to the power system below. At steady state the generator regulates the generating station voltage (bus 1) to pu. The system voltage at bus 3 is 1.05 pu. 1. Compute the internal voltage and rotor angle of the generator under the above conditions. 2. The fault sequence for a solid three-phase fault on any of the line circuits consists of a delayed tripping of both circuit...

  • Styles AC Bus Local Loads T: OC Bus PV Generating DC/AC Station Zline Local Power Grid...

    Styles AC Bus Local Loads T: OC Bus PV Generating DC/AC Station Zline Local Power Grid Inverter T1 T2 Figure Q2 In the microgrid in figure Q2, a solar PV station and the local power grid supply a series of local loads The PV generating station is rated at 2 MW and is operating at unity power factor. The PV station internal impedance is purely resistive equal to 50% based on its own rating of 2 MVA. The inverter DC...

  • Problem #1: A single-circuit, 500 kV, 60 Hz, three-phase transmission line is 250 km long. The...

    Problem #1: A single-circuit, 500 kV, 60 Hz, three-phase transmission line is 250 km long. The characteristic parameters of the transmission line are: x0.4 0/km At full load, the line delivers 1000 MVA at 500 kV with 0.80 PF lagging y j4 x 10 S/km r0.045 /km a. Assume that identical shunt reactors (inductors) are connected from each phase conductor to neutral at both ends of the line during light-load conditions, providing 50% total shunt compensation. The reactors are removed...

  • 4- - a 3-phase load of 500 MVA ,120 KV at 0.8 p.f lagging find: -...

    4- - a 3-phase load of 500 MVA ,120 KV at 0.8 p.f lagging find: - The magnitude of line current I Line – Three-phase (real) power Pload - Phase a |1ine) = ? 30, 500 MVA, 0.8 pf lagging line-to-line Phaseb Phasec

  • a five bus system

    The equipment ratings for a five bus system are given as Generator G1: 50 MVA, 12 kV, Xd ’’=X2=0.20, X0= 0.10 per unit Generator G2: 100 MVA, 15 kV, Xd ’’=0.2, X2=0.23, X0= 0.10 per unit Transformer T1: 50 MVA, 10 kV (Y)/138 kV (Y), X=0.10 per unit Transformer T1: 100 MVA, 15 kV (∆)/138 kV (Y), X=0.10 per unit Each 138 kV line: X1=40 Ohms, X0=100 ohms (1) Draw out the zero-, positive-, and negative- sequence reactance diagrams for the original system using a 100-MVA,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT