Question

Instructions A construction company is negotiating on a construction project with a six month duration. On the last day of ea
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution: Given Problem details the total income and expenditure for a project for 6 months and it is required to calculate t

The detailed calculation is shown below:

Cash Inflow
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
Bill to Owner 0 33000 63200 79800 46800 33000 19200
Holdback 5% 0 1650 3160 3990 2340 1650 960
Total Inflow 0 31350 60040 75810 44460 31350 32950
Cash Outflow
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
Materials 0 8800 14200 21000 6800 5100 4100
Labor 8100 11900 19800 7600 7000 4100
SubContr 0 13100 31400 31700 28100 17900 9300
Holdback 0 655 1570 1585 1405 895 465
Total Outflow 8100 33800 65400 60300 41900 27100 19975
Cashflow -8100 -2450 -5360 15510 2560 4250 12975
Cumulative -8100 -10550 -15910 -400 2160 6410 19385

Hence the maximum cash invested is obtained from cumulative value which is $15,910.

Add a comment
Know the answer?
Add Answer to:
Instructions A construction company is negotiating on a construction project with a six month duration. On...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Construction Project Cash Flow Activity A construction company is negotiating a construction project with a six-month...

    Construction Project Cash Flow Activity A construction company is negotiating a construction project with a six-month duration. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. The owner also holds 10% retention. Final Payment is expected one month after completion of the project and includes payment of the retention. The construction company pays material suppliers in...

  • A construction company is negotiating on a construction project with a three-month duration. On the last...

    A construction company is negotiating on a construction project with a three-month duration. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. Final payment is expected one month after completion of the project and will include the retention. The construction company pays material suppliers in full when they receive payment from the owner. The construction company...

  • A construction company decides to take a new job. The estimated income and expenses of this...

    A construction company decides to take a new job. The estimated income and expenses of this job are shown in the table below. The company is using Percentage Of Completion (POC) accounting method. The bills received by this company at the different months are shown below. Please determine the following:[40 points 6. The anticipated gross profit and percentage (%) in the table below a. b. The percentage of the project completion at the end of the 1t AND 2ad months...

  • 6. A construction company decides to take a new job. The estimated income and expenses of...

    6. A construction company decides to take a new job. The estimated income and expenses of this job are shown in the table below. The company is using Percentage of Completion (POC) accounting method. The bills received by this company at the different months are shown below. Please determine the following: [40 points] a. The anticipated gross profit and percentage (%) in the table below b. The percentage of the project completion at the end of the 1" AND 2nd...

  • Please check if my answers are correct or not for the multiple choice .. A. The owner to pay on a weekly basis ) The owner to pay on a monthly basis C. The owner D. The contracto 56. Arizona's Pr...

    Please check if my answers are correct or not for the multiple choice .. A. The owner to pay on a weekly basis ) The owner to pay on a monthly basis C. The owner D. The contracto 56. Arizona's Prompt Pay law requires: to pay at certain percentages of completion r to provide a guaranteed maximum price an 57. When a subcontractor submits a bid to the contractor, it constitutes Meeting of the Minds Consideration A. C Offer D....

  • alls Corners Construction Limited (BCCL) specializes in the construction of commercial buildings. A typical construction project...

    alls Corners Construction Limited (BCCL) specializes in the construction of commercial buildings. A typical construction project lasts between fifteen and twenty-four months. The company uses the percentage-of-completion method of revenue recognition since, given the characteristics of the contractor's business, it is the most appropriate method. Progress toward completion is measured on a cost-to-cost basis. BCCL follows ASPE and has a December 31 year-end. On January 1, 2016, the company began work on a contract and, at the beginning of the...

  • CE413 CONSTRUCTION METHODS Due 4/24/2017 I. A contractor has a five-month project with the expected direct costs as...

    CE413 CONSTRUCTION METHODS Due 4/24/2017 I. A contractor has a five-month project with the expected direct costs as follows: 1 month 25,000, 2d month $40,000, 3d month $65,000, 4th month $80,000, and 5th month $30,000. It is assumed that ( 1 ) the monthly indirect cost is $6,000, (b) retainage is 10% for the first three months, and 0% thereafter; (c) the markup is 25%; and, (d) the monthly interest rate is 1%. The contractor submits payment requests at the...

  • Select the best option to acquire construction equipments: Red Bird Construction company is considering three different...

    Select the best option to acquire construction equipments: Red Bird Construction company is considering three different acquisition methods for obtaining pickup trucks. Interest rate: 8% 1) Option A: Immediate cash purchase the trucks for $16,800 each, and after 4 years sell each truck for an estimated $5,000. 2) Option B: To lease the trucks for 4 years for $4,100 per year paid in advance at the beginning of each year. The contractor pays all operating and maintenance costs for the...

  • S9-12 (similar to) Stampede Corporation is preparing its cash payments budget for next month. The following...

    S9-12 (similar to) Stampede Corporation is preparing its cash payments budget for next month. The following information pertains to the cash payments: (Click the icon to view the data.) How much cash will be paid out next month? i More Info Stampede Corporation Cash Payments Budget Cash payments for direct materials: 50% of last month's purchases 50% of next month's purchases Cash payments for direct labor Cash payments for manufacturing overhead Cash payments for operating expenses Cash payment for taxes...

  • Aaron, owner of ABC Development LLC (ABC), filed a lawsuit against XYZ Construction Company (XYZ)...

    Aaron, owner of ABC Development LLC (ABC), filed a lawsuit against XYZ Construction Company (XYZ). The suit claims XYZ used substandard materials for the construction of 201 homes. After four years of arbitration, the case was finally settled for $50,000 in mid-2018. Over the four year period, there were partial payments from XYZ : Partial Settlement Disburse- ments Funds Remaining 2015 5 1 4 2016 5 2 3 2017 5 3 2 2018 35 29 6 50 35 15 The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT