Question

A construction company decides to take a new job. The estimated income and expenses of this job are shown in the table below. The company is using Percentage Of Completion (POC) accounting method. The bills received by this company at the different months are shown below. Please determine the following:[40 points 6. The anticipated gross profit and percentage (%) in the table below a. b. The percentage of the project completion at the end of the 1t AND 2ad months . The revenue AND the profit AND the profit percentage [%] at the end of the 1st month d. \Determine the gross profit percentage (%) using cash, accrual, and completed ontract methods at the end of the 1st month, If the company billed an invoice to customer $50,000, received cash $30,000 from customer, and paid out ($10,000) to suppliers at the end of 1st month. Anticipated Fixed Price Contract (3-month job) Gross Profit % Anticipated income Anticipated costs Anticipated gross profit $ Amount $130,000.00 ($100,000.00) ?? 23 Receive bills ($25,000.00) Receive bills ($40,000.00) Receive bills ($25,000.00) Project timeline 1st month 2nd month rd month
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Hey,

Please find enclosed solution. Hope this helps. In case of any further doubts, please comment on the solution.

Thank you.

SOLUTION

Clipboard r Font Alignment Number Styles H8 | Question 6a. Anticipated Gross profit and % Anticipated Gross profit Anticipated Income-Anticipated Costs $130,000 $100,000 30,000.00 4 Anticipated Gross profit% Anticipated Gross Profits100/ Anticipated Income $30,000 *100 $130,000 23.08% 10 Question 6b. % of Proiect Completion at the end of 1st and 2nd Month10 Question 6b. % of Project Completion at the end of 1st and 2nd Month Costs Already Incurred Total Anticipated Costs % of P21 22 Question 6c. Revenue and Profit and Profit% at end of 1st Month 23 24 25 26 27 28 29 30 31 32 33 Question 6d. Gross Profits at end of 1st Month 34 Anticipated Revenue 25% of $130,000 32,500.00 25,000.00 7,500.00 Costs Incurred Profits Profit % 23.08%32 33 Question 6d. Gross Profits at end of 1st Month 34 35 36 37 38 39 40 Cash Accrual Completed Contract Revenue 30000 50000 $32,500.00 Costs Incurred 10000 25000 $25,000.00 42 43 Profits Profit % 20000 67% 25000 50% 7500 23% Sheet1

Add a comment
Know the answer?
Add Answer to:
A construction company decides to take a new job. The estimated income and expenses of this...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 6. A construction company decides to take a new job. The estimated income and expenses of...

    6. A construction company decides to take a new job. The estimated income and expenses of this job are shown in the table below. The company is using Percentage of Completion (POC) accounting method. The bills received by this company at the different months are shown below. Please determine the following: [40 points] a. The anticipated gross profit and percentage (%) in the table below b. The percentage of the project completion at the end of the 1" AND 2nd...

  • A construction company is negotiating on a construction project with a three-month duration. On the last...

    A construction company is negotiating on a construction project with a three-month duration. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. Final payment is expected one month after completion of the project and will include the retention. The construction company pays material suppliers in full when they receive payment from the owner. The construction company...

  • alls Corners Construction Limited (BCCL) specializes in the construction of commercial buildings. A typical construction project...

    alls Corners Construction Limited (BCCL) specializes in the construction of commercial buildings. A typical construction project lasts between fifteen and twenty-four months. The company uses the percentage-of-completion method of revenue recognition since, given the characteristics of the contractor's business, it is the most appropriate method. Progress toward completion is measured on a cost-to-cost basis. BCCL follows ASPE and has a December 31 year-end. On January 1, 2016, the company began work on a contract and, at the beginning of the...

  • Construction Project Cash Flow Activity A construction company is negotiating a construction project with a six-month...

    Construction Project Cash Flow Activity A construction company is negotiating a construction project with a six-month duration. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. The owner also holds 10% retention. Final Payment is expected one month after completion of the project and includes payment of the retention. The construction company pays material suppliers in...

  • Problem 6 (12 points) Beck Construction Company began work on a new building project on January 1, 2016. The proje...

    Problem 6 (12 points) Beck Construction Company began work on a new building project on January 1, 2016. The project is to be completed by December 31, 2021, for a fixed price of $105 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Year Actual Cost Incurred each year Estimated to complete 2019 $ 20 million $ 80 million 2020 $ 45 million $ 25...

  • Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on...

    Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The bullding was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates...

    Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...

  • Problem 2 Tyler Company is a construction company that specializes in kitchen and bathroom remodels. Their...

    Problem 2 Tyler Company is a construction company that specializes in kitchen and bathroom remodels. Their policy is to require at 25% deposit for any job costing $10,000 or more, with payment due in full within 30 days of completion. Tyler Company’s accountants were gathering information to prepare the financial statements for the year 2017. They found the following information: On May 1, 2017, the company purchased a one-year insurance plan for $3,600. Coverage started on the date of purchase....

  • In 2020, Dixon Construction Company was awarded a contract to construct an interchange on Highway 30...

    In 2020, Dixon Construction Company was awarded a contract to construct an interchange on Highway 30 at a total contract price of $15,000,000. Construction is expected to take two years to complete. The estimated total costs of the project are $12,000,000. Dixon uses the percentage-of-completion method to account for long-term contracts. During the first year cost of construction totaled $7,200,000 and the total estimated costs for the project are unchanged. a)   Prepare the entry to record 2020 construction costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT