Question

Problem 6 (12 points) Beck Construction Company began work on a new building project on January 1, 2016. The project is to be
ANSWERS 2019 Gross Profit (Loss) Recognized 2020 Gross Profit (Loss) Recognized 2021 Gross Profit (Loss) Recognized
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Solution:

Computation of % of completion, revenue recognition and Gross Profit - Beck Construction (In Millions)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G - A)
2019 $20 $20 $100 20.00% $105 $21 $21 $1
2020 $45 $65 $90 72.22% $105 $76 $55 $10
2021 $34 $99 $99 100.00% $105 $105 $29 -$5
Add a comment
Know the answer?
Add Answer to:
Problem 6 (12 points) Beck Construction Company began work on a new building project on January 1, 2016. The proje...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Construction began on January 1, 2018. Expected completion date: December 31, 2020 Contract price $108 million....

    Construction began on January 1, 2018. Expected completion date: December 31, 2020 Contract price $108 million. The Completed Contract Method is used to recognize revenue and profit from the contracts. Years Actual costs incurred in each year Estimated remaining costs to complete the project (as of Dec 31) 2018 2019 2020 $40 million $38 million $36 million $60 million $44 million $ 0 What amount of gross profit (loss) would the company recognize in each year from the above contract?...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

  • 1) Indiana Co. began a construction project in 2021 with a contract price of $150 million...

    1) Indiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. In 2022, Indiana incurred additional costs of $58.5 million and estimated an additional $40.5 million in costs to complete the project. Required: Compute the % complete along with the revenue and gross profit to...

  • Exercise 5-18 Long-term contract; revenue recognition over time vs. upon project completion [LO5-9] On June 15,...

    Exercise 5-18 Long-term contract; revenue recognition over time vs. upon project completion [LO5-9] On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.С., for $270 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 $ 50 $100 60...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...

  • Question 2 Ivanhoe Construction entered into a contract to construct a bridge for a contract price...

    Question 2 Ivanhoe Construction entered into a contract to construct a bridge for a contract price of $2.80 million. Construction began in 2019 and was completed in 2021. Below are the details of the transactions related to the contract: 2019 2020 $653,000 $806,000 1,436,600 541,000 2021 $709,900 Costs incurred during the year Estimated costs to complete Calculate the revenue, expenses and gross profit to be recognized each year using the percentage-of-completion method. (Round the percentage completion to 2 decimal places,...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,300,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete (As of the End of the Year) Costs Incurred During Year Situation 2018 2019 2020 2018 2019 2020 11,530 2,220 990 3,210 990 2 1,530 990 2,520...

  • Brady Construction Company contracted to build an apartment complex for a price of $6,100,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $6,100,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs Incurred During Year Situation 2018 2019 2020 1,610 2,460 1,230 1,610 1,230 2,840 3 1,610 2,460 2,480 4 6103,110 1,220 610 3,110 2,070 6 610 3,110 2,900 Estimated Costs to...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2020. lust in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2018 2019 2020 $ 60 $130 $70...

  • it says it's incomplete, please help On February 1, 2018, Arrow Construction Company entered into a...

    it says it's incomplete, please help On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,600,000. During 2018, costs of $2,200,000 were incurred with estimated costs of $4,200,000 yet to be incurred. Billings of $2,700,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,700,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,950,000 and $2,675,000 cash was collected. The project was completed...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT