Question

Birdies produces four different models of footwear (detailed production information is provided in table below). The operations manager knows that total monthly demand exceeds the capacity available for production. Demand next month is estimated to be 200 units of model Blackbird, 250 units of model Heron, 150 units of model Starling, and 225 units of model Hummingbird. Birdie operates only one 8-hour shift per day and is scheduled to work 20 days next month (no overtime). Further, each station requires a 10 percent capacity cushion.

Product Station 1 Station 2 Station 3 Station 4 Blackbird 10 min 10 min 5 min 20 min 15 min 5 min Heron Starling Hummingbird

The bottleneck utilization is ___________ % (enter response rounded to one decimal place).

Flag this Question

Question 30.25 pts

Birdies produces four different models of footwear (detailed production information is provided in table below). The operations manager knows that total monthly demand exceeds the capacity available for production. Demand next month is estimated to be 200 units of model Blackbird, 250 units of model Heron, 150 units of model Starling, and 225 units of model Hummingbird. Birdie operates only one 8-hour shift per day and is scheduled to work 20 days next month (no overtime). Further, each station requires a 10 percent capacity cushion.

Product Station 1 Station 2 Station 3 Station 4 Blackbird 10 min 10 min 5 min 20 min 15 min 5 min Heron Starling Hummingbird

The profit produced from bottleneck method is $________________ (enter integer).

Flag this Question

Question 40.25 pts

Birdies produces four different models of footwear (detailed production information is provided in table below). The operations manager knows that total monthly demand exceeds the capacity available for production. Demand next month is estimated to be 200 units of model Blackbird, 250 units of model Heron, 150 units of model Starling, and 225 units of model Hummingbird. Birdie operates only one 8-hour shift per day and is scheduled to work 20 days next month (no overtime). Further, each station requires a 10 percent capacity cushion.

Product Station 1 Station 2 Station 3 Station 4 Blackbird 10 min 10 min 5 min 20 min 15 min 5 min Heron Starling Hummingbird

The profit produced from the traditional method is $___________ (enter integer).

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Traditional method

Step 1: Identify bottleneck station

Capacity of each station = 20 days*8 hours*60 minutes

= 9600 minutes

Available capacity net of 10% Capacity cushion = 9600*(1-10%)

= 8640 minutes

Load of station 1 = 200*10+250*0+150*5+225*20 = 7250 minutes

Load of station 2 = 200*5+250*20+150*15+225*5 = 9375 minutes

Load of station 3 = 200*15+250*10+150*5+225*10 = 8500 minutes

Load of station 4 = 200*10+250*0+150*20+225*10 = 7250 minutes

Load of station 2 is greater than Available Capacity.

Therefore, station 2 is the bottleneck.

Step 2: Determine profit of each product

Profit of Blackbird = 80-10 = $ 70

Profit of Heron = 95-10 = $ 85

Profit of Starling = 90-8 = $ 82

Profit of Hummingbird = 70-5 = $ 65

Step 3: Determine product mix

Product mix is prioritized on the basis of profit, giving highest priority to product with highest profit and lowest priority to product with least profit.

Based on profit, the priority is: Heron, Starling, Blackbird and Hummingbird

Available minutes on bottleneck station after production of first three products = 8640 - (250*20+150*15+200*5) = 390 minutes

Quantity of Hummingbird that can be produced in remaining time = 390 / 5 = 78 units

Therefore, optimal product mix is:

Blackbird = 200

Heron = 250

Starling = 150

Hummingbird = 78

Total profit using traditional method = 200*70+250*85+150*82+78*65 = $ 52,620

------------------------------------------------------------------

Bottleneck method

Step 1: Identify bottleneck station

As already identified in previous section, station 2 is the bottleneck.

Step 2: Determine profit per minute of bottleneck time for each product

Profit per minute of bottleneck time for Blackbird = 70/5 = $ 14

Profit per minute of bottleneck time for Heron = 85/20 = $ 4.25

Profit per minute of bottleneck time for Starling = 82/15 = $ 5.47

Profit per minute of bottleneck time for Hummingbird = 65/5 = $ 13

Step 3: Determine product mix

Product mix is prioritized on the basis of profit per minute of bottleneck time, giving highest priority to product with highest profit per bottleneck minute and lowest priority to product with least profit per bottleneck minute.

Based on profit per bottleneck minute, the priority is: Blackbird, Hummingbird, Starling, and Heron

Available minutes on bottleneck station after production of first three products (Blackbird, Hummingbird, Starling) = 8640 - (200*5+225*5+150*15) = 4265 minutes

Quantity of Heron that can be produced in remaining time = 4265/20 = 213 units

Therefore, optimal product mix is:

Blackbird = 200

Heron = 213

Starling = 150

Hummingbird = 225

Total profit using traditional method = 200*70+213*85+150*82+225*65 = $ 59,030

-----------------------------------------------------------------------------------------------------------------------------------------

Q1. The bottleneck (implied) utilization is = load of bottleneck station / available capacity

= 9375 / 8640

= 108.51 %

Q2. The profit produced from bottleneck method is $ 59,030

Q3. The profit produced from traditional method is $ 52,620

Add a comment
Know the answer?
Add Answer to:
Birdies produces four different models of footwear (detailed production information is provided in table below). The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cooper River Glass Works​ (CRGW) produces four different models of desk lamps as shown on the...

    Cooper River Glass Works​ (CRGW) produces four different models of desk lamps as shown on the flowchart. The operations manager knows that total monthly demand exceeds the capacity available for production.​ Thus, she is interested in determining the product mix which will maximize profits. Each​ model's price,​ routing, processing​ times, and material cost is provided in the flowchart. Demand next month is estimated to be 300 units of model​ Alpha,150 units of model​ Bravo, 175 units of model​ Charlie, and...

  • Summer-Fun, Inc., produces a various commodities related to recreation and leisure. The production manager has developed...

    Summer-Fun, Inc., produces a various commodities related to recreation and leisure. The production manager has developed an aggregate forecast: Apr May Aug Sep Total Mar June July Demand 50 1 44 | 55 | 59 | 50 | 41 51 350 Use the following information to develop aggregate plans. Regular production cost $ 80 per unit Overtime(OT) production cost $ 120 per unit Subcontracting(SC) cost $ 140 per unit Regular capacity 40 units per month Overtime capacity 8 units per...

  • Cooper River Glass Works (CRGW) is a company that produces artisanal glass products such as vases,...

    Cooper River Glass Works (CRGW) is a company that produces artisanal glass products such as vases, lamps, stained-glass, and art-glass installations. When it began lamp production a few years ago, it entered with a single product, the highly successful "Alpha" model. The process workflow for Alpha production is shown below along with the processing times at each station, material costs, MSRP, and typical weekly demand. Alpha → Step 1 @ station 1 (10 minutes) → Step 2 @ station 2...

  • (Process with Rework) Consider the following three-stage production process of glass ceramics, wh...

    Matching supply with Demand (3rd Edition) - Question 10.2 (Process with Rework) Consider the following three-stage production process of glass ceramics, which is operated as a worker-paced line. Q10.2 Components 6 min./unit 5 min./unit min. /unit Finished Units Rework The process is experiencing severe quality problems related to insufficiently trained work- ers. Specifically, 20 percent of the parts going through operation 1 are badly processed by the operator. Rather than scrapping the unit, it is moved to a highly skilled...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Nowjuice, Inc., produces bottled pomegranate juice. A planner has developed an aggregate forecast for demand for...

    Nowjuice, Inc., produces bottled pomegranate juice. A planner has developed an aggregate forecast for demand for the next six months. Month             May                Jun                  jul                    Aug                 Sep                  oct Forecast           4000                4800                5600                7200                6400                5000 Use the following information to develop aggregate plans. Regular production cost          $ 10 per case Regular production capacity   5000 cases Overtime production cost       $ 16 per case Subcontracting cost                $ 20 per case Inventory cost                         $ 1 per case per month Beginning inventory               0 Develop...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below....

    Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below. Cost of regular production is $5 per unit, the cost of producing the same unit on overtime is $7.50, the cost of subcontracting is S9 per unit, an<d the cost of carrying a unit in inventory from one month to the next is $2 The labor contract at the plant prohibits overtime output to exceed 300 units in any five month window (that is...

  • Please answer only the empty boxes (bottom table and the questions below it) The total subtracting cost= $_______ The t...

    Please answer only the empty boxes (bottom table and the questions below it) The total subtracting cost= $_______ The total inventory holding cost for January through August= $_____ The total​ cost, excluding normal time labor​ costs, for Plan E= $_____ Will thumps up if answers is correct! The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 1,400 1,700 May 2,300 January February 2,300 June March 1,700 1,700 July April...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT