Which one of the following indicators offers the best assurance that a project will produce value for its owners?
1) Pl equal to zero
2) Positive IRR
3) Negative rate of return
4) Positive AAR
5) Positive NPV
Which one of the following indicators offers the best assurance that a project will produce value...
Which one of the following is FALSE for a project whose NPV equals zero? Group of answer choices The project will have no impact on firm value. The project earns more than the required return. The IRR is equal to the required rate of return The projects cash outflows are equal to the present value of the cash inflows.
4. If an investment project has an IRR equal to the interest rate, the NPV for that project a. is positive b. is negative c. is zero. The NPV vs. r graph shows this best. d. may be negative or positive
(NPV, PI, and IRR calculations) Fijisawa Inc. is considering a major expansion of its product line and has estimated the following free cash flows associated with such an expansion. The initial outlay would be $1,800,000, and the project would generate incremental free cash flows of $600,000 per year for 5 years. The appropriate required rate of return is 8 percent. a. Calculate the NPV. b. Calculate the Pl. c. Calculate the IRR. d. Should this project be accepted? a. What...
Which one of the following projects should you accept? A project with an IRR of 12.7 percent and a required return of 13 percent. B. A project with an NPV of -$121.21. C. A project with a PI of 1.03. D. A project with an AAR of 13.8 percent and a required AAR of 14 percent.
Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR Cash Flow......($200).....$850....($700)......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Accept the project because the payback is short b. Accept the project because the NPV is greater than zero c. Reject the project because the IRR is less than the required rate of return d. Reject the project because...
80. Which one of the following should be assumed about a project that requires a $100,000 investment at time zero, then returns S20,000 annually for 5 years? A. The NPV is negative. B. The NPV is zero. C. The profitability index is 1.0. D. The IRR is negative.
please include parts a - d , thanks (NPV, PI, and IRR calculations) Fijisawa Inc. is considering a major expansion of its product line and has estimated the following cash flows associated with such an expansion. The initial outlay would be $2,000,000, and the project would generate incremental free cash flows of $550,000 per year for 6 years. The appropriate required rate of return is 9 percent. a. Calculate the NPV b. Calculate the Pl c. Calculate the IRR. d....
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Group of answer choices A) If a project's IRR is positive, then its NPV must also be positive. B) A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost. C) If a project's IRR is smaller than the WACC, then its NPV will be positive....
18. Which of the following is NOT true about the internal rate of return: A) A good project is one with IRR greater than the required return. B) IRR is the discount rate that results in a zero net present value for the project. C) Crossover rate for two projects is the IRR of the project with the difference of the cash flows of the two projects.. D) For two projects of the same size, IRR will usually choose the...
Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year...................0..............1...............2...........IRR Cash Flow.....($200).....$850.......($700).......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Reject the project because the NPV is less than zero b. Accept the project because the IRR is greater than zero c. Accept the project because the NPV is greater than zero d. Accept the project because the payback...