We will solve this linear programming problem using Excel solver as shown below
c)
We will setup excel as below
We will setup Solver as below
c)
Company can make profit of $6,590 (as per Solver optimal solution)
d)
Company should add team to Fab and Assembly team where hours constraint is restricting in meeting required orders
e)
We will first calculate total hours required for each team to meet the current orders
Basic Shed | Superior Shed | Deluxe Shed | |
Units required | 15 | 10 | 15 |
135.5 | # of hours required by Fab and Assembly team |
57.5 | # of hours required by Paint team |
55.5 | # of hours required by Inspection team |
Numbers of hrs currently available are
105 | # of hours available Fab and Assembly team |
70 | # of hours available Paint team |
60 | # of hours available Inspection team |
If we add one team to Fab and Assembly team
Revised optimal solution is below (we made capacity required same as capacity available for each team to meet the order demand)
Minimum number of team needed for each resource pool is
Hrs required | # hrs available per day per team | # of teams needed | |
Fab and Assembly Team | 135.5 | 7 | 135.5/(7*5)= 3.87 |
Paint Team | 57.5 | 7 | 57.5/(7*5)=1.64 |
Inspection Team | 55.5 | 6 | 55.5/(7*5)=1.59 |
f)
Looking at Solver solution, we can see that Deluxe Shed profit is highest among all sheds and it is most profitable.
Please give thumbs up if you like my answer. Thank you!
Problem 2 The Amazing Shed Company produces three different kinds of sheds: The Basic, The Superior,...
Albany Machinery manufactures two products, Basic and Superior, and applies overhead on the basis of direct labour hours. Anticipated (budgeted) overhead and direct labour time for the upcoming accounting period are $1,510,000 and 37,600 hours, respectively. Information about the company’s products follows: Basic: Estimated product volume 4 800 units Direct material cost $26 per unit Direct labour per unit 3 hours at $13 per hour Superior: Estimated product volume 5 800 units Direct material cost $62 per unit Direct labour...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 450,000 $46,800,000 Prime costs $10,800,000 Machine hours 150,000 750,000 $57,600,000 900,000 2,000 200 1,800 Engineering hours Receiving orders Inspection hours 300 900 1,200 800 1,600 2,400 Overhead costs: Machining Engineering $9,000,000 860,000 468,000 Receiving Inspecting products 480,000 Required: 2. Calculate the unit...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 130,000 390,000 — Prime costs $9,880,000 $42,120,000 $52,000,000 Machine hours 130,000 650,000 780,000 Engineering hours 500 4,500 5,000 Receiving orders 500 1,500 2,000 Inspection hours 1,000 2,000 3,000 Overhead costs: Machining $8,580,000 Engineering 3,000,000 Receiving 440,000 Inspecting products 360,000 Required: 1. Calculate the...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 140,000 420,000 ------ Prime costs $9,800,000 $44,520,000 $54,320,000 Machine hours 140,000 700,000 840,000 Engineering hours 400 3,600 4,000 Receiving orders 400 1,200 1,600 Inspection hours ...
Cost Assignment and IT Bunker Company produces two types of glucose monitors (basic and advanced). Both pass through two producing departments: Fabrication and Assembly. Bunker also has an Inspection Department that is responsible for testing monitors to ensure that they perform within prespecified tolerance ranges (a sampling procedure is used). Budgeted data for the three departments are as follows: Inspection Fabrication Assembly Overhead $560,000 $840,000 $238,000 Number of tests 35,000 105,000 Direct labor hours 84,000 42,000 In the Fabrication Department,...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 90,000 270,000 — Prime costs $6,480,000 $30,240,000 $36,720,000 Machine hours 90,000 450,000 540,000 Engineering hours 400 3,600 4,000 Receiving orders 500 1,500 2,000 Inspection hours ...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 Prime costs 450,000 $46,800,000 750,000 $10,800,000 150,000 $57,600,000 Machine hours 900,000 2,000 200 1,800 Engineering hours Receiving orders 300 1,200 Inspection hours 800 1,600 2.400 Overhead costs: $9,000,000 860,000 Machining Engineering Receiving Inspecting products 468,000 480,000 Required: 1. Calculate the four activity...
Activity Based Product Costing Total Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining engineering, receiving and inspection Information on these activities and their drivers is given below. Basic Advanced Units produced 120,000 360,000 Prime costs $10,000,000 543,200,000 $53.280,000 Machine hours 120.000 600,000 720.000 Engineering hours 300 2,700 3,000 Receiving orders 900 Inspection hours 900 1.800 2,700 Overhead costs: Machining 10. 58,640,000 1.230,000 Engineering 11 324,000 12. Inspectre products 351,000 13. Required: 14 FOOTTI...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 140,000 420,000 Prime costs $11,760,000 $50,400,000 $62,160,000 Machine hours 140,000 700,000 840,000 Engineering hours 3,600 4,000 Receiving orders 300 1,200 Inspection hours 1,800 2,700 400 900 900 Overhead costs: Machining $9,240,000 2,240,000 Engineering Receiving 240,000 Inspecting products 297,000 Required: 1. Calculate the four...
eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 300,000 100,000 $8,000,000 Prime costs $30,000,000 $38,000,000 Machine hours 100,000 500,000 600,000 Engineering hours 400 3,600 4,000 Receiving orders 400 1,200 1,600 Inspection hours 800 1,600 2,400 Overhead costs: Machining Engineering Receiving Inspecting products $6,000,000 2,000,000 560,000 360,000 Required: 1. Calculate...