Hi,
Can you provide the exact answers in details for this problem:
Calculate the accounting, cash, and financial break-even quantities.
Here is the problem:
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value of $650,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $350 per ton. The engineering department estimates you will need an initial net working capital investment of $510,000. You require a return of 14 percent and face a tax rate of 25 percent on this project. Calculate the accounting, cash, and financial break-even quantities.
Thank you,
Carol
1) | Contribution margin per unit = 350-240 = | $ 110 | |
Fixed costs = Depreciation+Other fixed operating cost = 5300000/6+1275000 = | $ 21,58,333 | ||
Accounting BEP in units = Total fixed costs/CM unit = 2158333/110 = | 19621 | Units | |
2) | Cash BEP in units = Cash fixed costs/CM unit = 1275000/110 = | 11591 | Units |
3) | Financial BEP in units, is the number of units that will result in 0 NPV. | ||
The PV of known Cash flows are: | |||
INITIAL INVESTMENT: | |||
Cost of the equipment | $ 53,00,000 | ||
Increase in NWC | $ 5,10,000 | ||
Total initial investment | $ 58,10,000 | ||
TERMINAL NON OPERATING CASH INFLOWS: | |||
After tax salvage value = 650000*(1-25%) = | $ 4,87,500 | ||
PV of after tax salvage value = 487500/1.14^6 = | $ 2,22,098 | ||
PV of after tax fixed costs = 1275000*75%*(1.14^6-1)/(0.14*1.14^6) = | $ 37,18,538 | ||
PV OF DEPRECIATION TAX SHIELD: | |||
= (5300000/6)*25%*(1.14^6-1)/(0.14*1.14^6) = | $ 8,58,747 | ||
NPV of known cash flows = -5810000+222098+858747 = | $ -84,47,693 | ||
The PV of the after tax annual contribution margin should be | $ 84,47,693 | ||
Annual after tax contribution margin = 8447693*0.14*1.14^6/(1.14^6-1) = | $ 21,72,388 | ||
Before tax contribution margin = 1216138/75% = | $ 28,96,517 | ||
Number of units to be sold = 2896517/110 = | 26332 | Units | |
CHECK: | |||
Total CM = 26332*110 = | $ 28,96,517 | ||
Depreciation = 5300000/6 = | $ 8,83,333 | ||
Other fixed costs | $ 12,75,000 | ||
NOI | $ 7,38,183 | ||
Tax at 25% | $ 1,84,546 | ||
NOPAT | $ 5,53,638 | ||
Add: Depreciation | $ 8,83,333 | ||
OCF | $ 14,36,971 | ||
PV of OCF = 1436971*(1.14^6-1)/(0.14*1.14^6) = | $ 55,87,902 | ||
PV of after tax salvage value = 487500/1.14^6 = | $ 2,22,098 | ||
Total PV of cash inflows | $ 58,10,001 | ||
Less: Initial investment | $ 58,10,000 | ||
NPV | $ 1 | ||
Almost 0 |
Hi, Can you provide the exact answers in details for this problem: Calculate the accounting, cash,...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1.275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
This problem concerns the effect of taxes on the various break-even measures. Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4,400,000 investment in threading equipment to get the project started; the project will last for three years. The accounting department estimates that annual fixed costs will be $650,000 and that variable costs should be $250 per ton; accounting will depreciate the initial fixed asset investment straight-line to...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,700,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,375,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,700,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,375,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production. You will need an initial $5,500,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,325,000 and that variable costs should be $250 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,700,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,375,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,300,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,525,000 and that variable costs should be $290 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production. You will need an initial $5,900,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,425,000 and that variable costs should be $270 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
If we consider the effect of taxes, then the degree of operating leverage can be written as: DOL = 1 + [FC × (1 – TC) – TC × D]/OCF Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...