Question

This problem concerns the effect of taxes on the various break-even measures. Consider a project to supply Detroit with 30,00

0 0
Add a comment Improve this question Transcribed image text
Answer #1

CASH BREAK EVEN QUANTITY
At the cash break-even, the OCF is zero. Setting the tax shield equation equal to zero and solving for the
quantity, we get:
OCF = [(selling price per unit– variable cost per unit)Quantity- Fixed cost](1- tax rate) + tax rate(initial investment/ number of years)

OCF = 0 = [($390 – $250)QC– $650,000](0.70) + 0.30($4,400,000/3)
0 = (140QC - 650,000)0.7 + 440,000
0 = 98QC-455000 + 440000
98QC= 15000
QC = 153.06
CASH BREAK EVEN QUANTITY = 153


ACCOUNTING BREAK EVEN QUANTITY
The accounting breakeven is calculated as:
QA =[fixed costs+ (initial investment/ number of years)]/(selling price per unit– variable cost per unit)
QA = [$650,000 + ($4,400,000/3)]/($390 – 250)
QA= 2116666.67/ 140
QA= 15,119.05
ACCOUNTING BREAK EVEN QUANTITY = 15,119


FINANCIAL BREAK EVEN QUANTITY
Using the tax shield approach, the OCF is:
OCF = [($390 – 250)(30,000) – $650,000](0.70) + 0.30($4,400,000/3)
OCF= (4200000- 650000)0.7 + 440,000
OCF= 2485000 + 440000
OCF = $2,925,000
And the NPV is:
NPV= - initial investment- net working capital + OCF (PVIFA)RATE OF RETURN, NO. OF YEARS) + + [net working capital - salvage value (1 – tax rate)]/(1 + rate of return no of years)
NPV = –$4,400,000 – 440,000 + $2,925,000(PVIFA18%,3)
+ [$440,000 + $260,000(1 – .30)]/1.183
NPV= –$4,400,000 – 440,000 + $2,925,000( 2.1743)
+ [$440,000 + $260,000(1 – .30)]/1.643032
NOV = -4840000 + 6359827.5 + 258000/1.643032
NPV= -4840000 + 6359827.5 + 157026.765
NPV = $1,676,854.265‬
To calculate the sensitivity to changes in quantity sold, we will choose a quantity of 35,000. The OCF at
this level of sales is:
OCF = [($390 – 250)(35,000) – $650,000](0.70) + 0.30($4,400,000/3)
OCF= (4900000- 650000)0.7 + 440,000
OCF= 2975000 + 440000
OCF = $3,415,000
The sensitivity of changes in the OCF to quantity sold is:
ΔOCF/ΔQ = ($$2,925,000 – 3,415,000)/(30,000 – 35,000)
ΔOCF/ΔQ = - $490000/-5000
ΔOCF/ΔQ = +98
The NPV at this level of sales is:
NPV == –$4,400,000 – 440,000 + $3,415,000(PVIFA18%,3)
+ [$440,000 + $260,000(1 – .30)]/1.183
NPV= –$4,400,000 – 440,000 + $3,415,000( 2.1743)
+ [$440,000 + $260,000(1 – .30)]/1.643032
NOV = -4840000 + 7425234.5 + 258000/1.643032
NPV= -4840000 + 7425234.5 + 157026.765
NPV = $2,742,261.265‬
And the sensitivity of NPV to changes in the quantity sold is:
ΔNPV/ΔQ =( $1,676,854.265‬- $2,742,261.265‬))/(30,000 – 35,000)
ΔNPV/ΔQ = -$1,065,407/ -5000‬
ΔNPV/ΔQ = +$213.08
You wouldn’t want the quantity to fall below the point where the NPV is zero. We know the NPV changes
$213.08 for every unit sold, so we can divide the NPV for 30,000 units by the sensitivity to get a change in
quantity. Doing so, we get:
$1,676,854.265‬= $213.08 (ΔQ)
ΔQ = 7869.59 = 7870
For a zero NPV, we need to decrease sales by 7870 units, so the minimum quantity is:
QF= 30,000 – 7870
FINANCIAL BREAK EVEN QUANTITY = 22,130‬
NOTE: As per given instructions intermediate calculations are not rounded off. End calculation are rounded off to nearest whole number

Add a comment
Know the answer?
Add Answer to:
This problem concerns the effect of taxes on the various break-even measures. Consider a project to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1.275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Hi, Can you provide the exact answers in details for this problem: Calculate the accounting, cash,...

    Hi, Can you provide the exact answers in details for this problem: Calculate the accounting, cash, and financial break-even quantities. Here is the problem: Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,700,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,375,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will ne...

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,700,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,375,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production. You will need an initial $5,500,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,325,000 and that variable costs should be $250 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,700,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,375,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,300,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,525,000 and that variable costs should be $290 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production. You will need an initial $5,900,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,425,000 and that variable costs should be $270 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • If we consider the effect of taxes, then the degree of operating leverage can be written...

    If we consider the effect of taxes, then the degree of operating leverage can be written as: DOL = 1 + [FC × (1 – TC) – TC × D]/OCF Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and...

  • If we consider the effect of taxes, then the degree of operating leverage can be written...

    If we consider the effect of taxes, then the degree of operating leverage can be written as: DOL = 1 + [FC × (1 – TC) – TC × D]/OCF Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production. You will need an initial $6,100,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,475,000 and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT