A proposed embankment fill requires 5000 m3 of compacted soil. The void ratio of the compacted...

A proposed embankment fill requires 5000 m3 of compacted soil. The void ratio of the compacted fill is specified as 0.75. Soil can be transported from one of the four borrow pits as shown in the table below. The void ratio, specific gravity of soil solids, and the cost per cubic meter for moving the soil to the proposed construction site are provided in the table.

a. Determine the volume of each borrow pit soil required to meet the specification of the embankment site.

b.Make necessary calculations to select the borrow pit which would be most cost effective.

Borrow pit

Void ratio

Gs

Cost ($/m3)

I

0.8

2.65

9

II

0.9

2.68

6

III

1.1

2.71

7

IV

0.85

2.74

10

0 0
Add a comment Improve this question Transcribed image text
Answer #1

2.65 0.1 1.1 0-8万 才. Gび9、8) 5000y 부4476-01-245t q.gl.14-4. ECTroutPred.-CE) |个1.1150 ·51台,8 m3 5431 53 65 2.곳 13. 83 291 -SI | 59799, Sm3 53 斗67994.11. 2.チが9

Add a comment
Know the answer?
Add Answer to:
A proposed embankment fill requires 5000 m3 of compacted soil. The void ratio of the compacted...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem Description A 20 m wide, 2km long, and Im thickness embankment should be constructed for...

    Problem Description A 20 m wide, 2km long, and Im thickness embankment should be constructed for a railway project in Melbourne city. The required soil for the embankment construction will be transported from a borrow pit located in a rural site. The borrow pit has loosely compacted sandy loam soil. Porosity of this borrow pit's soil is 0.40 and the specific gravity is 2.7. Part A; In order to maintain the stability of the railway project the embankment needs to...

  • Specifications of a road embarkment requires the soil to be compacted to a moist unit weight...

    Specifications of a road embarkment requires the soil to be compacted to a moist unit weight of 19.2kN/m3 at a moisture content of 17.5%.the soil is to be obtained from a borrow area where the in situ dry unit weight is 15.9 kN/m3. The volume of the finished embarkment is to be 1520m3. What volume of the borrow material is required for the road embarkment? It is assumed that the volume of tye fill be essentially unchanged when it is...

  • You may also assume a unit volume of soil, V, 1m3, for this problem. (5) Supplemental...

    You may also assume a unit volume of soil, V, 1m3, for this problem. (5) Supplemental Homework Problem Soil from a borrow site is used to place 2000 cubic meters of fill at a construction site. The soil properties for the borrow and fill are given below. Given: Borrow: Fill: (a) (b) Change in void ratio Ae between the borrow and fill 1690, Yr-173kN/m2 Gs 2.72 w w-1696, r,-181kN/m3 Find: Vr from borrow to place 2,000 m3 of fill Use...

  • the only question to answer are 2-5 2-7 2-10 2-17 2-19 thank you CHAPTER Two 2-3....

    the only question to answer are 2-5 2-7 2-10 2-17 2-19 thank you CHAPTER Two 2-3. An undisturbed chunk of soil has a wet weight of 62 lb and a volume of o.s6 ft. When dried out in an oven, the soil weighs S0 Ib. If the specific gravity o solids is found to be 2.64, determine the water con- tent, wet unit weight of soil, dry unit soil. 2-13. The wet unit weight of a soil sample is 18.55...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT