Question

Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capaci
If the Edwards production plan for the next period includes 1025 units of component 1 and 825 units of component 2, what purc
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Applying excel solver on above data:

Order quantity:
Component 1 2 3 total qty constraint total
1 200 0 825 1025 = 1025
2 350 475 0 825 = 825
550 475 825
constraint <= 550 1025 825
slack 0 550 0
total cost = 20200

from above

Supplier:
Component 1 2 3
1 200 0 825
2 350 475 0
Add a comment
Know the answer?
Add Answer to:
Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 4-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers....

    Problem 4-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company's needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows Supplier Component $10 $14 $10 $12$12 $10 Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as Edwards provides sufficient...

  • Problem 4-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers...

    Problem 4-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company's needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 13 1 $12 $13 510 2 $11 $12 s10 Each supplier has a limited capacity in terms of the total number of components it can supply. However,...

  • Edwards Manufacturing Company purchases two component parts from three different suppliers The suppliers have limited...

    Edwards Manufacturing Company purchases two component parts from three different suppliers The suppliers have limited capacity, and no one supplier can meet all the company's needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier                   Component 1 2 3                  1 $12 $13 $14 2 $10 $11 $10 Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as...

  • Problem 9-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers...

    Problem 9-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 3 1 $11 $12 $15 2 $11 $10 $11 Each supplier has a limited capacity in terms of the total number of components it can supply. However,...

  • Problem 9-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers...

    Problem 9-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 3 1 $11 $11 $13 2 $10 $12 $10 Each supplier has a limited capacity in terms of the total number of components it can supply. However,...

  • A linear programming computer package is needed. Edwards Manufacturing Company purchases two component parts from three...

    A linear programming computer package is needed. Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company's needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows. Supplier Component 2 1 $11 $12 $13 2 $9 $10 59 Each supplier has a limited capacity in terms of the total number of components it can...

  • Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in...

    Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in terms of quality in that the proportion or percentage of defective components may differ among the suppliers. To evaluate the proportion defective components for the suppliers, Benson has requested a sample shipment of 500 components from each supplier. The number of defective components and the number of good components found in each shipment is as follows. Supplier Component 10 35 Good 490 465 455...

  • Benson Manufacturing is considering ordering electronic components from three different suppliers...

    Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in terms of quality in that the proportion or percentage of defective components may differ among the suppliers. To evaluate the proportion defective components for the suppliers, Benson has requested a sample shipment of 500 components from each supplier. The number of defective components and the number of good components found in each shipment is as follows. Supplier Component A B C Defective 15 35...

  • Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in...

    Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in terms of quality in that the proportion or percentage of defective components may differ among the suppliers. To evaluate the proportion defective components for the suppliers, Benson has requested a sample shipment of 500 components from each supplier. The number of defective components and the number of good components found in each shipment is as follows. Supplier Component Defective Good 10 25 50 490...

  • Harley Davidson purchases components from three suppliers. Components purchased from Supplier A are priced at $...

    Harley Davidson purchases components from three suppliers. Components purchased from Supplier A are priced at $ 5 each and used at the rate of 206700 units per year. Components purchased from Supplier B are priced at $ 4 each and are used at the rate of 25,000 units per year. Components purchased from Supplier C are priced at  $ 5 each and used at the rate of 10,000 units per year. Currently Harley purchases a separate truckload from each supplier. As...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT