Question

Carlos Gonzales is production manager at an assembly plant that manufactures cordless telephones. The company is...

Carlos Gonzales is production manager at an assembly plant that manufactures cordless telephones. The company is planning to install a pull system. The process is being planned to have a usage rate of 30 pieces per hour. Each container is designed to hold 10 pieces. It takes an average of 25 minutes to complete a cycle. How many containers will be needed? (Calculate to 2 decimal places)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Demand rate, D = 30 per hour

Container size, K = 10

Lead time, L = 25 minutes = 25/60 = 0.4167 hour

Number of containers needed = D*L/K

= 30*0.4167/10

= 1.25

Add a comment
Know the answer?
Add Answer to:
Carlos Gonzales is production manager at an assembly plant that manufactures cordless telephones. The company is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In a winch assembly plant at Curt Manufacturing, the winch assembly work cell for the winch...

    In a winch assembly plant at Curt Manufacturing, the winch assembly work cell for the winch mount handle has a demand of 200 units an hour. Two feeder cells supply the two winch component parts CRT31005 and CRT 31006 to the assembly cell (one CRT31005 and one CRT31006 for each winch mount handle). Standard containers will hold 20 CRT31005’s or 10 CRT31006’s. It takes 10 minutes to fill up a container with CRT31005’s and 20 minutes to full up a...

  • Boehm Compressors uses a lean production assembly line to make its compressors. In one assembly area,...

    Boehm Compressors uses a lean production assembly line to make its compressors. In one assembly area, the demand is 100 parts per eight-hour day. It uses a container that holds eight parts. It typically takes about six hours to round-trip a container from one work center to the next and back again. It also desires to hold 15% safety stock of this part in the system. If it reduced the number of containers by one, how would this impact the...

  • Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly...

    Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly area, the demand is 200 parts per 8-hour day. It uses a container that holds 10 parts. It typically takes about 5 hours to round-trip a container from one work center to the next and back again. They also desire to hold a 20% safety stock of this part in the system. Based on the required safety stock of zero and the number of...

  • $ Nichols Inc, manufactures remote controls. Currently the company uses a plant - wide rate for...

    $ Nichols Inc, manufactures remote controls. Currently the company uses a plant - wide rate for allocating manufacturing overhead. The plant manager is considering switching - over to ABC costing system and has asked the accounting department to identify the primary production activities and their cost drivers which are as follows: Activities Cost driver Allocation Rate Material handling Number of parts $4 per part Assembly Labor hours $20 per hour Inspection Time at inspection station $10 per minute The current...

  • I AM COMPLETELY CONFUSED! Any help would be greatly appreciated. Chairvana’s Table Assembly Operations: Chairvana Inc....

    I AM COMPLETELY CONFUSED! Any help would be greatly appreciated. Chairvana’s Table Assembly Operations: Chairvana Inc. manufactures metal tables and chairs at its plant in Paxton, Illinois. Recently hired general manager, Bob Behar, is concerned about the large inventories and manufacturing inefficiencies in the plant. The Paxton plant has two separate assembly lines – one for chairs and one for tables. Demand for chairs is significantly larger than tables, so Bob decides to tackle the table assembly process for first....

  • Case Study 2 Motivation:   Production Slowdown at Bendum Metal Fab, Inc. Scenario: When the new supervisor...

    Case Study 2 Motivation:   Production Slowdown at Bendum Metal Fab, Inc. Scenario: When the new supervisor improves production dramatically at the expense of employee relations, the plant must face rumblings of rebellion. The incident calls for considering grievances, using authority, gaining acceptance of change, generating motivation, obtaining commitment, and linking output with job satisfaction. Incident: May B. Wright had been made supervisor of a production line at Bendum Metal Fabrication, Inc.(BMF). The plant manager, Sommer Flimsay, made her responsible for...

  • Doesn’t Time Fly! It was 7.30 on a Tuesday morning, when John Edwards, general manager of...

    Doesn’t Time Fly! It was 7.30 on a Tuesday morning, when John Edwards, general manager of the Jenkins Company’s main factory, turned on to the M3 to drive to his office in Basingstoke. The journey took about twenty minutes and gave John an opportunity to reflect on the problems of the plant without interruptions. The Jenkins Company ran three printing plants and had nationwide clients for its high-quality colour work. There were about 350 employees, almost half of whom were...

  • Should World Kitchen outsource Pyrex production and close the Charleroi plant? If so, how many suppliers should the company employ and where should they be located? We were una...

    Should World Kitchen outsource Pyrex production and close the Charleroi plant? If so, how many suppliers should the company employ and where should they be located? We were unable to transcribe this imagedishwas resulted from a process that pressed together yers of thin, strengthened opaque glass. products if they were moved overseas and simply source the lower-cost private-label versions directly sales and marketing functions. THE MARKET Givsn its extensive experience with outsourcing the Giobal Sourcing Department at World Kitchen had...

  • 109 CASE STUDY Dream Desk Compary Dream Desk Company is a major supplier of office desks for can ...

    109 CASE STUDY Dream Desk Compary Dream Desk Company is a major supplier of office desks for can profit from this market growth if prices can be held in line home and business. The company has been in existence since 1875. Affler serving an apprenticeship as a cabinet maker in the and quick delivery can be promised. Dream Desk operates a 250,000 sq. ft. manufacturing fa- cast, George Dreamer had a violent disagreement with the shop eility in Casa Petite,...

  • Summary should briefly analyze the central problems and issues of the case and provide some analysis...

    Summary should briefly analyze the central problems and issues of the case and provide some analysis and suggestions. Thank you. Lean Initiatives and Growth at Orlando Metering Company It was late August 2002 and Ed Cucinelli, vice president of Orlando Metering Company (OMC), sat in his office on a late Saturday morning. He had come in to prepare for some strategic planning meetings that were scheduled for the upcoming week. As he noticed the uncommon silence in the building, Ed...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT