This is the method of separating fixed and variable portion within a total cost.
The highest and lowest machine hours should be chosen for their respective costs; this is required for calculating variable cost per hour. The highest hour is in the month of January (180 hours), when the cost is $4,300; the lowest hour is in the month of June (50 hours), when the cost is $1,200.
Variable cost per hour = (Cost in the highest machine hour – Cost in the lowest machine hour) / (Highest machine hour – Lowest machine hour)
= ($4,300 - $1,200) / (180 – 50)
= $3,100 / 130
= $23.846
Fixed cost = Total cost for 180 hours – (Variable cost per hour × 180 hours)
= 4,300 – (23.846 × 180)
= 4,300 – 4292.28
= 7.7
In order of checking the above calculation, fixed cost could be founded in 50 hours
Fixed cost = Total cost for 50 hours – (Variable cost per hour × 50 hours)
= 1,200 – (23.846 × 50)
= 1,200 – 1,192.3
= 7.7 (tally)
a.
Required cost function (TC) should be as below:
TC = {Variable cost per unit × Machine hours (H)} + Fixed cost
TC = (23.846 × H) + 7.7
TC = 23.846H + 7.7 [Answer]
b.
In case of 130 machine hours:
TC = 23.846H + 7.7
= (23.846 × 130) + 7.7
= 3,099.98 + 7.7
= 3,107.68 (Answer)
In case of 220 machine hours:
TC = 23.846H + 7.7
= (23.846 × 220) + 7.7
= 5246.12 + 7.7
= 5,253.82 (Answer)
3. Jetboats Ltd uses the high-low method to estimate the cost function. Jetboat operates jet boat...
X Company uses the high-low method to estimate total overhead costs each month, with machine hours as the activity measure. The following past monthly cost and activity information is available: Cost Month May June July August $10,733 $8,973 $12,603 $14,253 Machine Hours 3,100 2,300 3,950 4,700 If machine hours in October are expected to be 4,000, what are estimated fixed overhead costs in October (round unit costs to two decimal places)? OA: $2,443 B: $2,858 C: $3,344 D: $3,913|| OE:...
Morrow Company uses the high-low method to estimate the cost function. The information for 2020 is provided below: Machine-hours Labor Costs Highest observation of cost driver 900 $36,000 Lowest observation of cost driver 100 $14,000 What is the estimated total cost when 450 machine-hours are used? A. 23,625 B.32,000 C. 18,000 D. 63,000
2. Uninder Company uses the high-low method to estimate the cost function. The information for 2019 is provided below: Machine-hours Labor Costs Highest observation of cost driver 475 $22,000 Lowest observation of cost driver 250 $13,000 What is the slope coefficient? A. $30.00 B. $32.00 C. $40.00 D. $43.75 E. $52.00
2. Uninder Company uses the high-low method to estimate the cost function. The information for 2019 is provided below: Machine-hours Labor Costs Highest observation of cost driver 475 $22,000 Lowest observation of cost driver 250 $13,000 What is the slope coefficient? A. $30.00 B. $32.00 C. $40.00 D. $43.75 E. $52.00
1. Uninder Company uses the high-low method to estimate the cost function. The information for 2019 is provided below: Machine-hours Labor Costs Highest observation of cost driver 475 $22,000 Lowest observation of cost driver 250 $13,000 What is the slope coefficient?" A. $52.00 B. $43.75 C. $30.00 D. $40.00. E.$32.00- e