If the Cost of Capital is equal to the Internal rate of return then Net Present Value will be equal to ZERO.
Answer Internal Rate of return
The discount rate which forces a projects NPV to be zero neutral rate of return or...
Question 2 1 pts The internal rate of return may be defined as Jh The discount rate that makes the project NPV equal to zero. The discount rate that makes the PV of the expected cash flows equal to the initial outlay. the market rate of interest less the risk free rate. a&b are both correct. a&care both correct Question 3 1 pts For independent projects, the NPV method and the IRR method will always lead to the same accept/reject...
Intemal rate of return (IRR) is computed by finding the discount rate that a. NPV of a project to be zero b. NPV of a project to be greater than zero c. NPV of a project to be less than zero d. IRR of a project to be zero Select one: a NPV of a project to be greater than zero
The internal rate of return is best described as that discount rate that _______ A equates the NPV and IRR B makes NPV equal zero C. equals the required rate of return D. equates all cash flows to the current market rate
Internal rate of return (IRR) is computed by finding the discount rate that will cause a. NPV of a project to be zero b. NPV of a project to be greater than zero c. NPV of a project to be less than zero d. IRR of a project to be zero Select one: a. NPV of a project to be less than zero b. NPV of a project to be zero c. NPV of a project to be greater than...
discount rate is zero percent? What if the discount rate is 5 percent? If it is 19 percent? 6. Calculating AAR (LO4) Youre trying to determine whether to expand your business by building a new manufacturing plant. The plant has an installation cost of $12 million, which will be depreciated straight-line to zero over its four-year life. If the plant has proiected net income of $1.854,300, $1,907.600, $1,876.000 and $1,329,500 over these four years, what is the project's average accounting...
Assuming a 10% discount rate, calculate the NPV of the four projects and rank the projects in order of preference. Show steps. 1. Growth Enterprise, Inc. (GEI) has $40 million that it can invest in any or all of the four capital investment projects (A, B, C, D), which have cash flows as shown in the following table. Table 1. Comparison of Project Cash Flows ($ thousand dollars) Project Type of Year 0 Year 1 Year 2 Year 3 cash...
You have been presented with 6 projects. All projects are 7-year projects. NPV Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI profitability index. Project F ($18,539) Project G $23,725 Project C $3,327 Project D $8,876 Project B $11,041 Project A $52,715 NPV 18.13% 11.77% 15.24% 43.46% 30.18% 21.71% IRR= 15.84% 12.97% 24.83% 20.12% 14.36% 17.16% MIRR= 0.94 1.12 1.02 1.89 1.44 1.21 Pl- If all projects are independent, which project or...
1. Calculate the net present value (NPV) for both projects, and determine which project should be accepted based on NPV. Round both NPVs to the nearest dollar. 2. Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR. 3. Calculate the net present value (NPV) for both projects using the crossover rate as your discount rate. Round both NPVs to the nearest dollar. Please show all work. Thank you. Use...
The internal rate of return is defined as the: O Discount rate that causes the profitability index for a project to equal zero. O Rate of return a project will generate if the project in financed solely with internal funds. O Discount rate that equates the net cash inflows of a project to zero. O Maximum rate of return a firm expects to earn on a project. O Discount rate which causes the net present value of a project to...
The internal rate of return is defined as the: A. discount rate that causes the profitability index for a project to equal zero. B. discount rate which equates the net present value of cash inflows to the net present value of cash outflows to zero. C. maximum rate of return a firm expects to earn on a project. D. rate of return a project will generate if the project in financed solely with internal funds.