Payback period calculation is the simple calcualtion for checking the | |||||
return of our Basis investment in year | |||||
CACULATION OF PAYBACK PERIOD | |||||
Period | Particulars | Inflow (Outflow) | PVF of $ 1 @ 10% | Present Value | Cumulative Present Value |
0 | Outflow | $ -45,000 | 1.00000 | $ -45,000.00 | $ -45,000.00 |
1 | Inflow | $ 15,000 | 0.90909 | $ 13,636.36 | $ -31,363.64 |
2 | Inflow | $ 15,000 | 0.82645 | $ 12,396.69 | $ -18,966.94 |
3 | Inflow | $ 15,000 | 0.75131 | $ 11,269.72 | $ -7,697.22 |
4 | Inflow | $ 15,000 | 0.68301 | $ 10,245.20 | $ 2,547.98 |
5 | Inflow | $ 15,000 | 0.62092 | $ 9,313.82 | $ 11,861.80 |
6 | Inflow | $ 15,000 | 0.56447 | $ 8,467.11 | $ 20,328.91 |
7 | Inflow | $ 15,000 | 0.51316 | $ 7,697.37 | $ 28,026.28 |
8 | Inflow | $ 15,000 | 0.46651 | $ 6,997.61 | $ 35,023.89 |
9 | Inflow | $ 15,000 | 0.42410 | $ 6,361.46 | $ 41,385.36 |
10 | Inflow | $ 15,000 | 0.38554 | $ 5,783.15 | $ 47,168.51 |
11 | Inflow | $ 15,000 | 0.35049 | $ 5,257.41 | $ 52,425.92 |
All the investment is recovered in the year 4 but not all the whole year is required for this | |||||
So the we have to calculate the fraction as below, | |||||
Payback Period = | 3 Years + | 7,697.2 | "/" By | $ 10,245.20 | |
Payback Period = | 3 Years + | 0.75 | |||
Payback Period = | 3.75 Years | ||||
Answer =Pay back period = 3.75 Years | |||||
Check My Work (3 remaining) Click here to read the eBook: Payback Period PAYBACK PERIOD Project...
Click here to read the eBook: Payback Period PAYBACK PERIOD Project L costs $40,000, its expected cash inflows are $9,000 per year for 7 years, and its WACC is 10%. What is the project's payback? Round your answer to two decimal places. years
Click here to read the eBook: Internal Rate of Return (IRR) IRR Project L costs $39,183.66, its expected cash inflows are $9,000 per year for 9 years, and its WACC is 11%. What is the project's IRR? Round your answer to two decimal places.
Check My Work (3 remaining) eBook Problem Walk-Through Project L requires an initial outlay at t 0 of $77,184, its expected cash inflows are $13,000 per year for 10 years, and its WACC is 10 %. What is the project's IRR? Round your answer to two decimal places. % Check My Work (3 remaining) MacBook Air
1. Problem 11.01 Click here to read the eBook: Net Present Value (NPV) NPV Project L costs $50,000, its expected cash inflows are $12,000 per year for 9 years, and its WACC is 11%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations.
Click here to read the eBook: Net Present Value (NPV) NPV Project L costs $50,000, its expected cash inflows are $11,000 per year for 7 years, and its WACC is 10%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations.
11-8: Payback Period Payback period Project K costs $70,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 14%. what is the project's payback? Round your answer to two decimal places. years
Check My Work (2 remaining) ) Click here to read the eBook: The Determinants of Market Interest Rates EXPECTED INTEREST RATE The real risk-free rate is 2.2%. Inflation is expected to be 3.5% this year, 4.75% next year, and 2.7% thereafter. The mtt ty risk premi s ese stato be as , 1 %, where t _ number of years to maturity what is the yield on a 7-year Treasury note? Do not round your intermed ate aalat ons Round...
Attempts: Keep the Highest: /1 1. Problem 11.01 Click here to read the eBook: Net Present Value (NPV) NPV Project L costs $35,000, its expected cash inflows are $15,000 per year for 10 years, and its WACC is 14%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations. Grade It Now Save & Continue Continue without saving
PAYBACK PERIOD Project L costs $45,000, its expected cash inflows are $12,000 per year for 9 years, and its WACC is 12%, what is the project's payback? Round your answer to two decimal places. years
PAYBACK PERIOD Project L costs $65,000, its expected cash inflows are $15,000 per year for 10 years, and its WACC is 14%. What is the project's payback? Round your answer to two decimal places. years