Question

Operations Management

Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows:

phpyQlSlO.png


0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:


June

July








1

2

3

4

5

6

7

8

Forecast

60

60

60

60

60

60

60

60

Customer Orders

52

38

23

12

0

0

0

0

Projected on hand inventory

48

88

128

68

108

148

88

128

MPS

100

100

100

0

100

100

0

100

ATP

48

62

65

0

100

100

0

100

Projected on hand inventory (POHI) = On-hand Inventory at the end of last week + MPS due at start of the week – Project requirements of that week

Week 1 = 0 +100 - 52 = 48

Week 2 = 48 +100 - 60 = 88

Week 3 =88+100 – 60 = 128

Week 4 = 128 – 60 = 68

Week 5 = 68 +100 - 60 = 108

Week 6 = 108 +100 – 60 = 148

Week 7 = 148 – 60 = 88

Week 8 = 88 +100 - 60 = 128

MPS is not used in Week 4 and Week 7 because POHI is not negative without it.         


ATP = MPS - Cumulative customer order until next MPS is used

Week 1 = 100 – 52 = 48

Week 2 = 100 - 38 = 62

Week 3 = 100 – (23+12) = 65

Week 4 = 0-0 = 0

Week 5 = 100 - 0 = 100

Week 6 = 100 - 0 = 100

Week 7 = 0 - 0 = 0

Week 8 = 100 - 0 = 100


answered by: Subrahmanyam golla
Add a comment
Know the answer?
Add Answer to:
Operations Management
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Prepare a master schedule given this information: It is now the end of week 1; customer...

    Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2,16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on- hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used (Leave no cells blank - be...

  • Prepare a master schedule given this information: It is now the end of week 1; customer...

    Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. (Leave no cells blank - be...

  • Prepare a master production schedule for industrial pumps in the manner of the following ta Use...

    Prepare a master production schedule for industrial pumps in the manner of the following ta Use the MPS rule to "schedule production when the projected on-hand inventory would be le than 10 without production". Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. 30 33 Week Forecast Customer orders (committed) Projected on- hand inventory MPS 0 Available to promise (ATP) 70 51 Question 29 (3 points) What is the projected...

  • Prepare a master schedule given this information: It is now the end of week 1; customer...

    Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2,16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. (Leave no cells blank-be certain to enter...

  • Prepare a master production schedule for industrial pumps in the manner of the following table. U...

    Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule to "schedule production when the projected on-hand inventory would be less than 10 without production, Suppose that a production lot size of 70 pumps is used (Leave no cells blank- be certain to enter "O wherever required.) June 64 Forecast Customer orders (commitied) Projected on-hand inventory MPS ATP 30 30 40 40 30 20 30 10 References eBook & Resources Worksheet...

  • needing help with Excel 3. Complete the master production schedule based on the following information: 1...

    needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...

  • Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and...

    Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...

  • Prepare a master schedule and an available to promise table given customer orders below. MPS is...

    Prepare a master schedule and an available to promise table given customer orders below. MPS is 85 units, and the company has 150 units to begin with. Forecast for the eight-period work duration is 75 units.                 Week 1 2 3 4 5 6 7 8 Customer Order 75 85 90 48 55 72 88 90

  • Part II. TECHHICHI PPUDICMS (SHOW ALL CHICHI WUIS UIT Law Problem 7. (10%) Using the information...

    Part II. TECHHICHI PPUDICMS (SHOW ALL CHICHI WUIS UIT Law Problem 7. (10%) Using the information in the following table, prepare a prospective MPS and calculate the available-to-promise quantities. The order policy is to produce in lots of 300. 1 100 40 2 100 190 3 100 220 Week 4 5 100 120 70 60 6 120 110 7 120 40 8 120 Quantity on hand: 100 Forecast Customer orders (CO) Projected on-hand inventory MPS quantity Available-to-promise (ATP) Assume that...

  • A company manufactures bookcases. In August (a four week month), they have a forecast of 66,800...

    A company manufactures bookcases. In August (a four week month), they have a forecast of 66,800 units of a particular SKU. They start the month with 22,000 units on the shelf. This is the MPS grid for the first two weeks: April 22000 1 2 3 4 Forecast 16700 16700 16700 16700 Customer Orders 12000 14000 7000 4000 Projected on-hand 10550 14850 MPS 5250 21000 Safety stock for this item is 10,000 boxes. Production is in fixed lots of 5,250...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT