Prepare a master schedule and an available to promise table given customer orders below. MPS is...

Prepare a master schedule and an available to promise table given customer orders below. MPS is 85 units, and the company has 150 units to begin with. Forecast for the eight-period work duration is 75 units.

               

Week

1

2

3

4

5

6

7

8

Customer Order

75

85

90

48

55

72

88

90

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Master Schedule showing MPS and ATP is following:

Formulas used in calculating On hand inventory and ATP are explained below:

Add a comment
Know the answer?
Add Answer to:
Prepare a master schedule and an available to promise table given customer orders below. MPS is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT