Prepare a master schedule and an available to promise table given customer orders below. MPS is 85 units, and the company has 150 units to begin with. Forecast for the eight-period work duration is 75 units.
Week |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
Customer Order |
75 |
85 |
90 |
48 |
55 |
72 |
88 |
90 |
Master Schedule showing MPS and ATP is following:
Formulas used in calculating On hand inventory and ATP are explained below:
Prepare a master schedule and an available to promise table given customer orders below. MPS is...
1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots your calculations on the paper to receive full or partial credits. of 100. Show all Week 4 7 50 20 8 50 10 2 5 6 Quantity on hand: 401 404040 50 95 Forecast Customer orders (booked) Projected on-hand Inventory MPS quantity Available-to-promise (ATP) 20 40 45 15 75...
Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...
Describe a master production schedule (MPS) and compute available-to-promise quantities.
The Master Production Schedule quantity ________. a. Is equal to Customer Orders b. Is equal to the higher of the Forecast and Customer Orders quantities c. Depends on the Available to Promise quantity d. None of the above
Prepare a master production schedule for industrial pumps in the manner of the following ta Use the MPS rule to "schedule production when the projected on-hand inventory would be le than 10 without production". Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. 30 33 Week Forecast Customer orders (committed) Projected on- hand inventory MPS 0 Available to promise (ATP) 70 51 Question 29 (3 points) What is the projected...
Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2,16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on- hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used (Leave no cells blank - be...
Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. (Leave no cells blank - be...
Show work Spring 2018 Name: LD. #: 1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots of 100. Show all your calculations on the paper to receive full or partial credits. Week Quantity on hand: 40 1 Forecast 40|40|40|40|50 50 | 50 | 50 Customer orders (booked)20 95 40 45 15 75 20 10 Projected on-hand Inventory MPS...
Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule to "schedule production when the projected on-hand inventory would be less than 10 without production, Suppose that a production lot size of 70 pumps is used (Leave no cells blank- be certain to enter "O wherever required.) June 64 Forecast Customer orders (commitied) Projected on-hand inventory MPS ATP 30 30 40 40 30 20 30 10 References eBook & Resources Worksheet...
Given the following information, the Available to Promise will show ________. Week 1 2 3 4 Forecast Demand 120 120 120 120 Actual Customer Orders 85 100 35 20 Available to Promise MPS 250 250 a. 130, 130, 130, 130 b. 165, 65, 30, 230 c. 130, 10, -110, 130 d. 30, 0, 0, 230