The Master Production Schedule quantity ________.
|
Answer: d. None of the above
Explanation:
MPS is depends on the customer order, forecast, lead time, and Lot size.
So it is not necessary that it is equal to customer order or higher of customer order or forecast.
Available to promise qty depends on MPS not vice versa.
The Master Production Schedule quantity ________. a. Is equal to Customer Orders b. Is equal to...
Prepare a master schedule and an available to promise table given customer orders below. MPS is 85 units, and the company has 150 units to begin with. Forecast for the eight-period work duration is 75 units. Week 1 2 3 4 5 6 7 8 Customer Order 75 85 90 48 55 72 88 90
Describe a master production schedule (MPS) and compute available-to-promise quantities.
Prepare a master production schedule for industrial pumps in the manner of the following ta Use the MPS rule to "schedule production when the projected on-hand inventory would be le than 10 without production". Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. 30 33 Week Forecast Customer orders (committed) Projected on- hand inventory MPS 0 Available to promise (ATP) 70 51 Question 29 (3 points) What is the projected...
needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...
Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...
Management Instructions Beginning Inventory 68 Safety Stock 300 Lot Size 144 Master Production Schedule Period 1 2 3 4 5 6 7 8 Demand 505 580 575 550 520 480 475 525 Customer Orders 710 660 570 330 100 515 80 40 Projected On-Hand Inventory (POHI) (at the end of the period) Master Production Schedule Available To Promise (1-period look ahead) Discrete Available To Promise (1-period look ahead) Cumulative
Quantities in the MPS row of the master production schedule correspond to ________ in the requirements schedules of their immediate inputs in the bill of materials. a. Scheduled Receipts b. Planned Order Receipts c. Gross Requirements d. None of the above
15. What is the production system that normally requires the most inventory of raw material items? A. Make-to-order B. Assemble-to-order C. Engineer-to-order D. Make-to-stock 16. Inside the demand time fence, which of the following is true? A. It is easy to change the master production schedule (MPS) B. Available-to-promise (ATP) calculations ignore customer orders and forecast C. New customer orders can only occasionally be accepted D. Marketing and logistics people could make any changes 17. The expected demand in October...
Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule to "schedule production when the projected on-hand inventory would be less than 10 without production, Suppose that a production lot size of 70 pumps is used (Leave no cells blank- be certain to enter "O wherever required.) June 64 Forecast Customer orders (commitied) Projected on-hand inventory MPS ATP 30 30 40 40 30 20 30 10 References eBook & Resources Worksheet...
Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2,16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on- hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used (Leave no cells blank - be...