Quantities in the MPS row of the master production schedule correspond to ________ in the requirements schedules of their immediate inputs in the bill of materials.
|
a. Scheduled Receipts
- The above option completes the statement.
Sincerely request you to please give me an upvote. Thanks in advance.
Quantities in the MPS row of the master production schedule correspond to ________ in the requirements...
Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and Material Requirements Planning (MRP) Tables Bill of Material (QPA) A =Finished Good LT=1 B (1 LT-3 C(2) LT=2 D(1) LT 2 LT-2 F (2) LT-2 G (1) LT=1 Answer the following questions: 1). Fill in MPS/MRP tables provided 2). For Part Number B: What is the first period in which there is a net requirement ?:_AND, What is the net requirement Quantity (in the...
Describe a master production schedule (MPS) and compute available-to-promise quantities.
Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. (Leave no cells...
In the following requirements schedule, X is equal to ________. Week 1 2 3 Gross Requirements 250 250 Scheduled Receipts 125 Available Inventory 180 X Net Requirements Planned Order Receipt 125 Planned Order Release 125 A. 0 B. 125 C. 180 D. 305
. Canvas ©OSA The master production schedule (MPS) translates the sales & operationsplan (SOP) into: Specific production orders Forecast demand Specific production plan Efficient lot sizes Question 25 A precedent relationship shows... The number of components required to produce an item The order in which production steps must be accomplished Only the first step of the production process Only the final step of the production process Question 26 In a material requirements planning (MRP) system, gross requirements are time phased,...
Please provide equation for each box
4.5. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for 100 Asto be available in week 5. There are 20 Bs available. All other on-hand balances =0. B(2) B (1) D(1) (1) D(2) RI) Part Number Week 3 1 2 4 5 100 Part Number Quantity B 2 D...
Q6) Hip Replacements, Inc., has a master production schedule for its newest model, as shown of 1 week. What are the costs of using (a) EOQ and (b) POQ for this 10-week period? below, setup cost of $50, a holding cost per week of $2, beginning inventory of 0, and lead time a addevajhy WEEK nd 10 2 4 6 Gross requirements Schedu ed receipts 50 35 100 15 C Projected on hand 24 0 0 14 24 14 14...
9. Immediate inputs to Capacity Requirements Planning include which of the following? I. Production plan II. Planned orders III. Scheduled receipts A. III only B. I and II only C. I and III only D. II and III only
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...