Question

9. Immediate inputs to Capacity Requirements Planning include which of the following? I. Production plan II....

9. Immediate inputs to Capacity Requirements Planning include which of the following?
I. Production plan
II. Planned orders
III. Scheduled receipts
A. III only
B. I and II only
C. I and III only
D. II and III only

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The critical inputs to Capacity Planning are essentially the Planned Orders that are in-hand or expected and the Scheduled outputs from the line. In-line with the above, the option D fits the requirements as it speaks about Planned orders & Scheduled receipts.

Add a comment
Know the answer?
Add Answer to:
9. Immediate inputs to Capacity Requirements Planning include which of the following? I. Production plan II....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Quantities in the MPS row of the master production schedule correspond to ________ in the requirements...

    Quantities in the MPS row of the master production schedule correspond to ________ in the requirements schedules of their immediate inputs in the bill of materials. a. Scheduled Receipts b. Planned Order Receipts c. Gross Requirements d. None of the above

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • CAPACITY PLANNING & MANAGEMENT

    Capacity Planning and Management Sample 2An office supply company makes notebooks with the following product structure:NOTEBOOK------PAD----COVER.  The company uses an MRP system and has the following records for these three itemsNotebookWeek123456Gross Requirements252525252525Scheduled ReceiptsProjected Balance Available305Planned Order Releases20252525250Quantity = L4L, Lead-time = 1, Safety Stock = 0PadWeek123456Gross Requirements20252525250Scheduled Receipts15Projected Balance Available1051015202525Planned Order Releases3030303000Quantity = 30, Lead-time = 1, Safety Stock = 0CoverWeek123456Gross Requirements20252525250Scheduled Receipts50Projected Balance Available10401540154040Planned Order Releases50050000Quantity = 50, Lead-time = 2, Safety Stock = 0The note books are fabricated in...

  • calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled...

    calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. Click the icon to view the MRP record. Complete the material requirements plan (enter your responses as whole numbers). Week .A2* LT(weeks) 3 2 6 1 Gross requirements Scheduled receipts Projected ending inventory: 360 350 100 50 100 220 0 Net requirements Min. order 1 Planned receipts Planned orders ulo iMore Info Week 2 4 5 6 3 A2** Gross requirements...

  • Materials Requirements Planning (MRP) Franklin Fan’s two most profitable products are the ceiling fan (CF151) and...

    Materials Requirements Planning (MRP) Franklin Fan’s two most profitable products are the ceiling fan (CF151) and the personal fan (PF032). With the rising popularity in home remodeling and personal comfort, Franklin Fan has enjoyed substantial demand for these two products. Last year, Kathryn Marley, the vice president of operations and supply chain management, approved the installation of a new MRP system. It is a first important step toward the eventual goal of a full-fledged ERP system. Marley worked closely with...

  • Problem 14-5 To simplify data handling to include the receipt of orders that have actually been...

    Problem 14-5 To simplify data handling to include the receipt of orders that have actually been placed in previous periods, the following six-level scheme can be used. (A number of different techniques are used in practice, but the important issue is to keep track of what is on hand, what is expected to arrive, what is needed, and what size orders should be placed.)      One unit of A is made of three units of B, one unit of C, and...

  • Which of the following can create a deadweight loss? i. production quotas ii. price floor iii....

    Which of the following can create a deadweight loss? i. production quotas ii. price floor iii. price ceiling A. i only B. i and iii C. ii and iii D. i, ii, and iii E. i and ii

  • Materials Requirements Planning (MRP) Franklin Fan’s two most profitable products are the ceiling fan (CF151) and...

    Materials Requirements Planning (MRP) Franklin Fan’s two most profitable products are the ceiling fan (CF151) and the personal fan (PF032). With the rising popularity in home remodeling and personal comfort, Franklin Fan has enjoyed substantial demand for these two products. Last year, Kathryn Marley, the vice president of operations and supply chain management, approved the installation of a new MRP system. It is a first important step toward the eventual goal of a full-fledged ERP system. Marley worked closely with...

  • Recently, Phil Harris, the production control manager at Brunswick, read an article on time phased requirements...

    Recently, Phil Harris, the production control manager at Brunswick, read an article on time phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine...

  • 18) Which of the following are key inputs to determining the current value of an asset?...

    18) Which of the following are key inputs to determining the current value of an asset? I. the required rate of return II. future cash flows III. current stock price IV. timing of future cash flows A) I and III only B) II, III and IV only C) I and II only D) I, II and IV only

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT