Question

CAPACITY PLANNING & MANAGEMENT

Capacity Planning and Management Sample 2

An office supply company makes notebooks with the following product structure:


NOTEBOOK------PAD----COVER. 


 The company uses an MRP system and has the following records for these three items

Notebook

Week

1

2

3

4

5

6

Gross Requirements


25

25

25

25

25

25

Scheduled Receipts








Projected Balance Available

30

5






Planned Order Releases


20

25

25

25

25

0

Quantity = L4L, Lead-time = 1, Safety Stock = 0


Pad

Week

1

2

3

4

5

6

Gross Requirements


20

25

25

25

25

0

Scheduled Receipts


15






Projected Balance Available

10

5

10

15

20

25

25

Planned Order Releases


30

30

30

30

0

0

Quantity = 30, Lead-time = 1, Safety Stock = 0



Cover

Week

1

2

3

4

5

6

Gross Requirements


20

25

25

25

25

0

Scheduled Receipts


50






Projected Balance Available

10

40

15

40

15

40

40

Planned Order Releases


50

0

50

0

0

0

Quantity = 50, Lead-time = 2, Safety Stock = 0


The note books are fabricated in the following work centres listed with accompanying time requirements

image.png

Determine the weekly capacity requirements in each of the work centres.

For the two scheduled receipts, assume that the setup is complete and that in each case they are half complete.

Your Answer should fit in the following table:

WorkCentre

Week

1

2

3

4

5

6

100







200







300







 PLEASE SHOW ALL THE POSSIBLE CALCULATIONS AS TO HOW THE ANSWER IS CALCULATED. DONT GIVE ONLY THE FINAL ANSWER IN THE TABLE. I WANT ALL THE CALCULATIONS SO I CAN UNDERSTAND HOW IT IS DONE. THANK YOU,

0 0
Add a comment Improve this question Transcribed image text
Answer #1

821 Q fx IF(B6>0,$C13,0)+B6*$D13/60+50.2 D13/60 1 Planned Order Releases Week 3 Item 4 Notebook Assembl 5 Pad Production 6 Co

EXCEL FORMULAS:

Weekly Capacity requirements
Week
Work Center 1 2 3 4 5 6
100 =IF(B4>0,$C11,0)+B4*$D11/60 =IF(C4>0,$C11,0)+C4*$D11/60 =IF(D4>0,$C11,0)+D4*$D11/60 =IF(E4>0,$C11,0)+E4*$D11/60 =IF(F4>0,$C11,0)+F4*$D11/60 =IF(G4>0,$C11,0)+G4*$D11/60
200 =IF(B5>0,$C12,0)+B5*$D12/60+15/2*D12/60 =IF(C5>0,$C12,0)+C5*$D12/60 =IF(D5>0,$C12,0)+D5*$D12/60 =IF(E5>0,$C12,0)+E5*$D12/60 =IF(F5>0,$C12,0)+F5*$D12/60 =IF(G5>0,$C12,0)+G5*$D12/60
300 =IF(B6>0,$C13,0)+B6*$D13/60+50.2*D13/60 =IF(C6>0,$C13,0)+C6*$D13/60 =IF(D6>0,$C13,0)+D6*$D13/60 =IF(E6>0,$C13,0)+E6*$D13/60 =IF(F6>0,$C13,0)+F6*$D13/60 =IF(G6>0,$C13,0)+G6*$D13/60
Add a comment
Answer #2

Operation

Work Center

Setup time

Run time

Notebook assembly

100

2 hrs

10 min

Pad production

200

3 hrs

5 min

Cover production

300

2 hrs

9 min


Notebook assembly:

Weekly capacity requirement for work centre 100

Requirement for week 1 = 2+20*10/60 = 5.33 hours

Requirement for week 2 = 2+25*10/60 = 6.17 hours

Requirement for week 3 = 2+25*10/60 = 6.17 hours

Requirement for week 4 = 2+25*10/60 = 6.17 hours

Requirement for week 5 = 2+25*10/60 = 6.17 hours

Requirement for week 6 = 0+0*10/60 = 0 hours


Pad production:

Weekly capacity requirement for work centre 200

Requirement for week 1 = 3+30*5/60+5*0.5*15/60 = 6.13 hours

Requirement for week 2 = 3+30*5/60 = 5.5 hours

Requirement for week 3 = 3+30*5/60 = 5.5 hours

Requirement for week 4 = 3+30*5/60 = 5.5 hours

Requirement for week 5 = 0+0*5/60 = 0 hours

Requirement for week 6 = 0+0*5/60 = 0 hours


Cover production:

Weekly capacity requirement for work centre 300

Requirement for week 1 = 2+50*9/60+9*0.5*50/60 = 13.25 hours

Requirement for week 2 = 0+0*9/60 = 0 hours

Requirement for week 3 = 2+50*9/60 = 9.5 hours

Requirement for week 4 = 0+0*9/60 = 0 hours

Requirement for week 5 = 0+0*9/60 = 0 hours

Requirement for week 6 = 0+0*9/60 = 0 hours


answered by: Harved
Add a comment
Know the answer?
Add Answer to:
CAPACITY PLANNING & MANAGEMENT
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item...

    One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...

  • Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct...

    Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER 0 4 50 5 70 75 40 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 75 50 70 Period Gross requirements Item J Scheduled receipts...

  • One unit of A is made of two units of B and one unit of C....

    One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...

  • Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item a...

    Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. (Leave no cells...

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • One unit of A is made of three units of B, one unit of C, and...

    One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...

  • Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time =...

    Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time = 1 week On-hand = 40 Safety stock = 20 Order quantity: FOQ = 100 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements 70 50 80 80 70 60 80 80 Scheduled receipts Available inventory Net requirements Planned order receipts Planned order releases

  • provide step by step explanation of calculation. thanks

    Case #2 MGT2315  There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT