Question

15. What is the production system that normally requires the most inventory of raw material items? A. Make-to-order B. Assemb

0 0
Add a comment Improve this question Transcribed image text
Answer #1

15. In assemble to order, the main inventory is of raw material which is assembled into the final products as desired by the customer, and there are few items in WIP or finished goods inventory.

B is correct.

16. C New customer orders can be occasionally accepted when there is some capacity available to promise.

17. Unites to be produced = demand -Inventory on hand + end inventory target

= 20000-1000 +3000 = 22000

Total units which can be produced by one worker in a month = 25x10 =250

Number of workers needed = 22000/25x10 =88

C is correct.

Add a comment
Know the answer?
Add Answer to:
15. What is the production system that normally requires the most inventory of raw material items? A. Make-to-order B....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and...

    Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...

  • Use the following three MPS's constructed by the master production scheduler of the company to an...

    Use the following three MPS's constructed by the master production scheduler of the company to answer the questions related to this problem. Explain all your answers! 6 30 30 20 20 20 Forecast Orders 10 30 20 IPAB l s | 25 | -5 | 20 | O-30- 60 I. 50 ATP 5 50 50 MPS 50 50 5 6 II. Forecast 30 30 25 20 20 20 Paragraph Orders РАВ ATP MPS 30 20 45 20 5050 10 25...

  • Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and...

    Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and Material Requirements Planning (MRP) Tables Bill of Material (QPA) A =Finished Good LT=1 B (1 LT-3 C(2) LT=2 D(1) LT 2 LT-2 F (2) LT-2 G (1) LT=1 Answer the following questions: 1). Fill in MPS/MRP tables provided 2). For Part Number B: What is the first period in which there is a net requirement ?:_AND, What is the net requirement Quantity (in the...

  • A company manufactures two types of DVD players, A and B. Although there are differences among...

    A company manufactures two types of DVD players, A and B. Although there are differences among the products, there are a number of common parts within each player. Each model A requires one subassembly C and two subassembly D’s. Each subassembly C requires two F’s and two G’s. Each subassembly D requires two units of F. Each F requires two units of raw material I, while each G requires one unit of raw material H. Each model B requires two...

  • please help:) Raw Material Inventory TASK-A (3 sec) TASK-B (17 sec) TASK-C (13 sec) TASK-D (7...

    please help:) Raw Material Inventory TASK-A (3 sec) TASK-B (17 sec) TASK-C (13 sec) TASK-D (7 sec) Finished Good Inventory Use the above information to answer the following questions: a) Assess which of the four tasks is the bottleneck for the system. Give reason. b) Determine the capacity (in units per hour) of the above system. Show working. c) Elegant Garment Company has received an order of 539,000 shirts for the next year. The company operates from 8:00 am to...

  • CASE STUDY Smartphone Production at QuickTronics Rudy Hartono, general manager at QuickTronics, a con- tract manufacturer...

    CASE STUDY Smartphone Production at QuickTronics Rudy Hartono, general manager at QuickTronics, a con- tract manufacturer for consumer electronics, was headed TABLE 8-13 to the annual planning meeting. He had the demand fore- cast for the next 12 months and the goal of the meeting was to develop an aggregate plan. Historically, Rudy had Month Demand Forecast for Smartphones (in '000s) Demand 8,000 10,000 11,000 11,000 11,000 12,000 13,000 14,000 15,000 17,000 19,000 19,000 maintained a steady workforce of 667...

  • #8 7. Suppose that Sam's Cat Hotel in the problem above uses a P system instead...

    #8 7. Suppose that Sam's Cat Hotel in the problem above uses a P system instead of a system. The average daily demand is d = 96/6 = 16 bags, and the standard deviation of daily demand is 0, od = 16 = To = 6.142 bags "week_15 a. What P (in working days) and T should be used to approximate the cost trade-offs of the EOQ? b. How much more safety stock is needed with a P system than...

  • 8. If a line is balanced with 80 percent efficiency, the "balance delay" will be: 20 percent. B. 80 pe...

    8. If a line is balanced with 80 percent efficiency, the "balance delay" will be: 20 percent. B. 80 percent. C. 100 percent. D. unknown, since balance delay is not related to efficieney. E. depends on the next operation. 9. A common goal in designing process layouts is: A. minimizing the number of workers. B. minimizing number of machines. minimizing transportation costs. maximizing workstation productive time E. maximizing transportation distances. 07) vnit 10. The maximum allowable cycle time is computed...

  • Acme Manufacturing Forecasting Analysis Paralysis Acme produces technology parts used by the manufacturers of self-driving vehicles....

    Acme Manufacturing Forecasting Analysis Paralysis Acme produces technology parts used by the manufacturers of self-driving vehicles. The primary demand for Acme’s four products is dependent on the output of the manufacturer’s MRP systems. Acme produces the required quantities for the manufacturers and ships them just-in-time to reach the production lines. Acme also must provide inventory to support the repair of vehicles after they are sold to consumers. To meet this additional demand, they augment their internal production plans by adding...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT