Question

Guide Stone Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B,...

Guide Stone Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department are as follows.

Department

Product 1

Product 2

Product 3

A

1.50

3.00

2.00

B

2.00

1.00

2.50

C

0.25

0.25

0.25

During the next production period, the labor-hours available are 450 in department A, 350 in department B, and 50 in department C. The profit contributions per unit are $25 for product 1, $28 for product 2, and $30 for product 3.

a.   Formulate a linear programming model for maximizing total profit contribution.

b.   Solve the linear program formulated in part (a). How much of each product should be produced and what is the projected total profit contribution?

c.   After evaluating the solution obtained in part (b), one of the production supervisors noted that production setup costs had not been taken into account. She noted that setup costs are $400 for product 1, $550 for product 2, and $600 for product 3. If the solution developed in part (b) is to be used, what is the total profit contribution after taking into account the setup costs?

d.   Management realized that the optimal product mix, taking setup costs into account, might be different from the one recommended in part (b). Formulate a mixed-integer linear program that takes setup costs into account. Management also stated that we should not consider making more than 175 units of product 1, 150 units of product 2, or 140 units of product 3.

e.   Solve the mixed-integer linear program formulated in part (d). How much of each product should be produced and what is the projected total profit contribution? Compare this profit contribution to that obtained in part (c).

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a)KI2 Profit 1 Decision variables 2 X1 3 X2 4 X3 MAX 0 Constraints labour hours for A labour hours for B labour hours for C Non negativity 450 350 50 0 0 0 0 > 10 12 13 15 16

b)

c)

Total profit contribution in b) = $5540.00

Total set up costs = $400+$550+$600 = $1550

Total profit contribution after setup costs = $5540 - $1550 = $3990

d)

Add a comment
Know the answer?
Add Answer to:
Guide Stone Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT