Question

Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with...

Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion​ time, the most likely completion​ time, and the pessimistic completion time​ (all in​ days) for a new contract are given in the following​ table:

Activity: a,b.c.d.e.f.g.h.i.j,k

Time.(Days ) A, M, B, predecessors

A= 2, 5, 9, zero

B= 10, 11, 12 zero

C= 1, 2, 3, Zero

D= 7, 8, 9, C

E= 1, 3, 5, BD

F= 7, 9, 14, AE

G= 2, 3, 4, AE

H= 3, 5, 7 F

I= 10, 11, 12 G

J= 15, 17, 19 C

K= 4, 8, 12 H,I

b)

1.Activities on the critical path for the project are B - E - F - H - K

.

2.The total project completion time is ....... days. ​(Round your response to two decimal​ places.)

​c) For the given​ project, the earliest start​ (ES) and earliest finish​ (EF) are:

​(Round your responses to two decimal​ places.)

ACTIVITY A TO J

Earliest Start.(ES) . from a-j

Earliest Finish (EF). from a-j

0 0
Add a comment Improve this question Transcribed image text
Answer #1

We will use below approach:

Expected time = (Optimistic + 4*Most Likely + Pessimistic)/ 6

Variance = ((Pessimistic - Optimistic)/ 6)2

Earliest Start Time (ES) = the earliest time that an activity can begin

Earliest Finish Time (EF) = the earliest time that an activity can be completed

EF = ES + duration of activity        

Latest Start Time (LS) = the latest time that an activity can begin without lengthening the minimum project duration

Latest Finish Time (LF) = the earliest time than an activity can be completed without lengthening the minimum project duration

LF = LS + duration of activity         

Duration of the project = the difference between the maximum value of the "latest finish time" of projects and the minimum value of the "earliest start time" of projects

Project duration = max(LF) - min(ES)     

Slack = the amount of time that a project can be delayed without increasing the duration of the project

Slack = LF- LS or EF - ES

Critical path is the path with Total Slack = 0

Expected time = (Optimistic + 4*Most Likely + Pessimistic)/ 6
Variance = ((Pessimistic - Optimistic)/ 6)2
Activity Predecessors Duration Exp. Duration Variance Early Start (ES) Early Finish (EF) Late Start (LS) Late Finish (LF) Slack Critical Path
Optimistic, a Most Likely, m Pessimistic, b Te σ2
A 2 5 9 5.2 1.36 0 5.2 8.8 14.0 9
B 10 11 12 11.0 0.11 0.0 11.0 0.0 11.0 0 Y
C 1 2 3 2.0 0.11 0.0 2.0 1.0 3.0 1
D C 7 8 9 8.0 0.11 2.0 10.0 3.0 11.0 1
E B, D 1 3 5 3.0 0.44 11.0 14.0 11.0 14.0 0 Y
F A, E 7 9 14 9.5 1.36 14.0 23.5 14.0 23.5 0 Y
G A, E 2 3 4 3.0 0.11 14.0 17.0 14.0 17.0 0
H F 3 5 7 5.0 0.44 23.5 28.5 23.5 28.5 0 Y
I G 10 11 12 11.0 0.11 17.0 28.0 17.0 28.5 1
J C 15 17 19 17.0 0.44 2.0 19.0 28.5 36.5 18
K H, I 4 8 12 8.0 1.78 28.5 36.5 28.5 36.5 0 Y
Activities on Critical path (Slack = 0 ) is B-E-F-H-K
Project expected duration is 36.5 days (same as critical path completion time)


Please give thumbs up/ likes if you find this answer helpful. Thank you!

Add a comment
Know the answer?
Add Answer to:
Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 5: For the given activity network, if there are 35 days required to complete the...

    Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • 3.19 Kelle C offices. Peter Kelle h time it took to complete several recent jobs. So...

    3.19 Kelle C offices. Peter Kelle h time it took to complete several recent jobs. So are very unreliable. A list of activities and their op pletion time, the completion time (all in days) for a new contract are given in following table: arpet and Trim installs carpet in commercial as been very concerned with the amount of com- most likely completion time, and the pessimistic timistic the

  • question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in...

    question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...

  • The table below shows the output from a system that uses PERT for project scheduling. The...

    The table below shows the output from a system that uses PERT for project scheduling. The project involves 12 interdependent activities and all times are reported in weeks. Based on the information provided, answer the following questions: IMMEDIATE EXPECTED ACTIVITY PREDECESSORS TIME EARLIEST EARLIEST LATEST LATEST START FINISH START FINISH 16 BNS lolos 12 4 31 28 43 32 10 6 38 D, J, K (a) What is the minimum expected time required to complete the project? (b) How is...

  • Given is a CPM project network diagram as shown below. A F Start E H End...

    Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day А 6 B 3 с 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)

  • QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E...

    QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E H End B D G Start A B C D E F G H End Activity day 0 6 زر 8 7 4 9 4 6 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • please show answers clearly 12 points Save Answer QUESTION 5 Given is a CPM project network...

    please show answers clearly 12 points Save Answer QUESTION 5 Given is a CPM project network diagram as shown below. F А H End E Start G B D E F Activity day Start 0 A 5 B 6 Ula G 5 H 4 End 0 ON 9 8 days. a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days.. c) The Latest Finish time, LF, of Acitivity C = d) The critical...

  • Given is a CPM project network diagram as shown below. Activity Start A B C D...

    Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 5 6 9 6 9 8 5 4 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days.. d) The critical activities are = (ex. Fill in answer as: ABCD) End Start

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT