a)Min expected time required to complete project=max value of latest finish time - min value of earliest start time=61-0=61
Hence it will take 61 weeks to complete project.
b)Here slack time for B is 8.Any activity with a slack/float time of zero is critical.Here B is not critical.Hence project time will not change.
c)Here H is critical activity as slack time is 0.Project duration will increase by 1 week.
d)Activity J is critical as slack time is 0.Project duration will be reduced and can be recalculated as follows:
As J is predecessor of L,we calculate early start
ES(L)=max[ES(D)+T(D),ES(J)+T(J),ES(K)+T(K)]
=max[10+6,43+6,32+6]
=49
Now completion time for project will be ES(L)+T(L)
=49+8=57
Hence project will be completed early by 61-57=4 weeks.
[Note ES is Earliest start time T is expected time]
The table below shows the output from a system that uses PERT for project scheduling. The...
Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15 me 10 13 12 20 a) The Project Completion time = b) The Earliest Start time, ES, of Activity F- c) The Earliest Start time, ES, of Activity K = d) The Latest Start time, LS, of Activity. E = e) The non-critical activities are comma, no space) (ex. type in critical activities as ABCD, no
Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End Time 0 1.35 3.65 4.327 .36 8.25 1.394 .68 3.250 a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, Es, of Activity G- (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C (in 2 decimal places) d) The critical activities are (ex. type in critical activities as ABCD no comma, no space)
Given all the information in the table, use PERT/CPM to help Mr.
Hawthorne address to the following questions.
A. Create the network diagram representing the problem.
B. What is the total time expected to be required to complete
the project if no delays occur?
C. What are the earliest and latest start and finish times for
the individual activities required to meet the expected project
completion time provided in question B (show your method for
determining this)?
D. Which are...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...
Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
Job Saint has laid out the major steps and eight activities to complete the wing assembly for an experimental air craft. These activities have been labeled A to H in the following table, which also shows their estimated completion time (in weeks) and immediate predecessors. Activity Immediate Predecessors a m b A --------- 1 2 3 B -------- 2 3 4 C A 4 5 6 D B 8 9 10 E C ...
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Activity Predecessor(s) Normal Time Crash Time Normal Cost $400 Crash Cost $700 1600 2000 800 1100 1000 NNW 600 1200 1450 800 800 500 650 400 600 900 1300 F G H1 1000 650 8. Draw the network for this project. (10 points) 9. Please indicate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish on the...