If the 400th unit is 60 hours and the 800th unit is 45 hours, then the learning curve is what percent?
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
If the 400th unit is 60 hours and the 800th unit is 45 hours, then the...
f 100 labor hours were required to make the 2nd unit in a production process and 60 labor hours were required to make the 10th unit, what was the learning-curve rate during the production process?
CHAPTER 6: LEARNING CURVE (MONDAY) 1. The unit improvement factor for a 60 percent learning curve at 25 units is 0.0933. The first and second timings of a person doing a job are 5 minutes and 3 minutes respectively. What is the learning-adjusted time estimate for unit number 25? 2. You have just timed a person doing a job a few times. The first time it took the person 25 minutes, the second time it took 20 minutes, and the...
What is the estimate of the cumulative average hours per unit required to produce the first 5 units of a production run that has a(n) 78% learning curve, if the first unit takes 61 hours? (HINT: skip unit)
The direct labor times required to produce the first unit was 5 hours. The fourth unit took 3.2 hours. what is the estimated learning or improvement rate? Answers: a. 68% b.80% c. 70% D. 60%
6. If it took 80 hours to produce the first unit of a product, and the learning rate is 80%, how long will it take to produce units 26 through 125? A. 1158.54 hours B. 1998.94 hours C. 1779.07 hours D. 2064.36 hours E Impossible to answer in the time allowed. 5. If it takes 60 hours to produce the first unit of a product and 50 hours to produce the 12th unit, what is the learning rate? A. 95.04%...
A job with a 95% learning curve required 19 hours for the second unit. The first unit should require approximately how many hours?
The total cumulative time for 60 units is 2500 minutes and the unit time for the first production unit is 85 minutes. Use the cumulative average curve approach: a.) determine the value of the slope ,b. b.) determine the learning rate (in percentage). Use the unit curve approach: a.) determine the value of the slope ,b. b.) determine the learning rate (in percentage). c.)
If 200 labor hours were required to produce the first unit in a production run, and n labor hours were required to produce the seventh unit. Find the value of n if the learning curve rate during production is 80%.?
If the tenth unit produced took 24 hours and the fifth unit took 32 hours, answer the following: a) What is the learning rate? b) How long did the first unit take to complete? c) How long did the third unit to take to complete?
If the tenth unit produced took 24 hours and the fifth unit took 32 hours, answer the following. a) What is the learning rate? b) How long did the first unit take to complete? c) How long did the third unit take to complete?