If 200 labor hours were required to produce the first unit in a production run, and...

If 200 labor hours were required to produce the first unit in a production run, and n labor hours were required to produce the seventh unit. Find the value of n if the learning curve rate during production is 80%.?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans) TN = T1 (Nb)

Where, TN is time for nth unit

T1 is time required for 1st unit.

b = (log of learning rate)/(log2)

TN = 200 (7(log0.8/log2)) = 200 × 7(-0.3219) = 200 × 0.5345 =106.8979

Add a comment
Know the answer?
Add Answer to:
If 200 labor hours were required to produce the first unit in a production run, and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT