If the cost of capital is 10%, what is the MIRR of this project and should be accepted or rejected?
Year 0 1 2 3 4 5 6
Cash Flow -$1000 200 400 600 600 200 600
6.76%, reject
20.87%, accept
21.72%, accept
32.12%, accept
None of the above
We use the formula:
A=P(1+r/100)^n
where
A=future value
P=present value
r=rate of interest
n=time period.
Hence future value of inflows=200*(1.1)^5+400*(1.1)^4+600*(1.1)^3+600*(1.1)^2+200*(1.1)^1+600
=$3252.342
MIRR=[future value of inflows/Present value of outflows]^(1/time period)-1
=[$3252.342/1000]^(1/6)-1
which is equal to
=21.72%(Approx).
Hence since MIRR is greater than cost of capital;project must be accepted.
If the cost of capital is 10%, what is the MIRR of this project and should...
HELP -All questions on page- The rest of question 43 is on the second picture 40. Using the payback method, what is the payback of this project? Year 12 3 600 400 6006002006 Cash -$1000 200 Flow A. O years B. 1.33 years C. 2.67 years D. 4.00 years E. 3.09 years If the cost of capital is 10%, what is the discounted payback of this project? 5 200 Year I o Cash -$1000 200 Flow 400 600 600 600...
Compute the MIRR statistic for Project I and note whether to accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 15 percent. Project I Time 0 1 2 3 4 5 Cash Flow –$ 1,000 $ 400 $ 300 $ 200 $ 300 $ 50 Multiple Choice The project's MIRR is 18.19 percent and the project should be accepted. The project's MIRR is 12.67 percent and the project should be...
Compute the MIRR statistic for Project lif the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project I Time: Cash flow: 0 -$11,300 1 $5,480 2 $4,330 3 $1,670 4 $2,150 MIRR % Should the project be accepted or rejected? rejected accepted
Compute the MIRR static for Project I if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project I Time: Cash flow: $11,000 $5,330 $4,180 $1,520 $2,000 MIRR % Should the project be accepted or rejected? accepted rejected
Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow: −$1,100 $380 $1,530 −$530 $330 −$110 Should the project be accepted or rejected? accepted rejected
MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which costs $2.5 million. Cash inflows of $13 million would occur at the end of Year 1. The land must be returned to its natural state at a cost of $11 million, payable at the end of Year 2. a. Plot the project's NPV profile. B NEY NPV Miliens of Dulles Men of Dole 200 3000WACC) 80 200 300 400 WACC) 200 300 400 WACC)...
Compute the payback statistic for Project B if the appropriate cost of capital is 10 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "O" (zero).) Project B Time: Cash flow: -512,900 12 $3,540 $4,560 $1,900 $0 $1,380 Payback years Should the project be accepted or rejected? accepted rejected < Prex 6 of 7 Ners > search OM
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculat your final answer to 2 decimal places.) Project E Time: Cash flow -$1,500 $550 2 $630 3 $620 4 $400 5 $200 IRR Should the project be accepted or rejected? • accepted rejected
MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which costs $1.5 million. Cash inflows of $13.5 million would occur at the end of Year 1. The land must be returned to its natural state at a cost $11 million, payable at the end of Year 2. a. Plot the project's NPV profile. NPV i Millions of Dollas) NPV (Millions of Dollas) | *** ****** NPV Millions of Dollar) | ********* * *** non...
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: -10-200 $3,900 $4,730 $2,070 $2,700 IRR % Should the project be accepted or rejected? O rejected O accepted