Chapter 6 from the book ( project management in practice, 6th edition ).
· Linking a group of projects together with pseudoactivities creates a sort of superproject. What does this mean, and why wou
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Just as a project consists of tasks and activities with precedence relationships, a super project can be thought of as consisting of a group of projects with precedence relationships. In the super project, pseudo activities are used to show the precedence relationships among the projects. These precedence relationships may be actual technological constraints (e.g., the product development project must be completed before the process development project) or simply a reflection of management’s priorities.

The reason for creating a super project is to help identify important relationships and dependencies across the projects and use this information to better plan the usage of key resources.

Add a comment
Know the answer?
Add Answer to:
Chapter 6 from the book ( project management in practice, 6th edition ). · Linking a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT